Our engineering in action
On the example of the floor arrangement for the largest transport and logistics center of Belarus "Prilesye"

CONCRETE TOPPING FLOOR IN A PRIVATE GARAGE IN THE MOSCOW REGION

WE HAVE SAVED FOR THE CLIENT 194 500

FLOOR ENGINEERING CONSTRUCTION Concrete floor with a hardener for a garage in the Shchelkovsky district

MO, Shchelkovsky district, cottage settlement "Losiny ostrov-1"
Characteristics and description
Company name
Private person
The purpose of the floor and the room itself
Concrete floor with a hardener for a garage in the Shchelkovsky district
Type of floor
topping floors
Thickness of the concrete layer
120 cm
Room area
115.9 m²

Customer needs AND THE OPTIMAL ENGINEERING SOLUTION

factors taken into account when developing the floor design

WE HAVE SELECTED THE OPTIMAL ENGINEERING SOLUTION

This time the object turned out to be an ordinary garage for a car in a private village, the customer, accordingly, is a private person.

Since the object in this case is non-industrial, the floor here was not required industrial. But the technology used was standard – a concrete floor with topping. The difference was that a special emphasis had to be placed on the beautiful appearance of the floor. Therefore, white topping from Rockland was used in the works.

Also, the work plan in the garage included the installation of a tray with a sand trap.

The following aspects are important to the customer:

Terms of work
Number of days for all work: 7
Requirements for the quality of work
Floors must comply with SNiP 2.03. 13-88
Appearance of floors
Must look presentable
Durability
Service life of floors without repair (years): 10
Total cost
Budget within the framework of: 972 600 ₽
Concrete floor with a hardener for a garage in the Shchelkovsky district: The object before the start of work
The object before the start of work

Floor arrangement ACCORDING TO THE ENGINEERING SOLUTION FOR THE OBJECT: Private person

how we implemented this floor design

FEATURES OF THE WORKS

As mentioned above, one of the stages of the work was to install a tray with a sand trap, which was made to order. We have been waiting for this stainless steel product worth several hundred thousand rubles for 2 weeks. But that's not all – when we received the tray, we found some moments, because of which it had to be sent back for revision. Only when the product was completely ready, we started work.

The difficulty here was that the customer demanded to complete the work before April 1, since after that date the gates for trucks would be closed in the private village. I.e. it would be impossible to drive in there with mixers. We handed over the object completely end-to-end, but on time.

The work was carried out in the locality. Neighbors lived nearby. I had to work at the agreed time.

The customer on his own, even before the start of our work, installed a warm floor over the entire area of the garage. It required careful work on our part so as not to damage anything.

OUR RESULTS

The client was satisfied with the quality of the final coverage, the payment was made quickly and on time.

Stages of implementation engineering design of the floor

engineering design of the floor
1.jpg
Delivered the tray to the facility
2.jpg
Foam trimming
3.jpg
Preparatory work
4.jpg
Delivered materials to the facility
5.jpg
Completing the fill
6.jpg
The seam cutting stage

The result of floor engineeringDELIVERED ON TIME, STANDARD, TECHNOLOGICAL INDUSTRIAL FLOORS AT THE FACILITY Private person

SEE THE RESULT OF OUR WORK
result-ramzes.jpg

READ REVIEWS OUR SATISFIED CUSTOMERS

Reviews that we managed to collect between production cycles at our facilities

ReviewsABOUT THE PROFTEHPOL PROJECT

We are well aware that reviews of companies can be very different. Working in the construction market for more than 15 years, we have faced various situations.

We have both satisfied customers and those who are not. But, there is one important thing: we always bring the cycles of our provision to the end. If a client has problems, then we do not leave him with them, but settle them to a full and final conclusion.

Working with us, you can be sure that we will make you an industrial floor that is exactly right for the task for which you needed it.

Thanks to a good knowledge of the technology of industrial floors, we have gathered a lot of practical experience in using floor structures in various difficult places. We solve non-trivial problems and often, when we take an order, 3-4 companies have already tried to take it before us, but refused due to the complexity of the object.

Our clients Which we are proud of

for which we have made good floors
Legal informationSociety Limited Liability "PROFTECHENGINEERING" Shareholdt International consumer society "GOLDEN AXIS"TIN 9709064635CHECKPOINT 770901001OGRN 1207700295406Legal address:109147, Moscow, B.Andronevskaya str., 23, building 1, floor 8, room 4, office of PROFTEHPOL company
POSTAL DETAILSActual address:109147, Moscow, B.Andronevskaya str., 23, building 1, floor 8, room 4, office of PROFTEHPOL companyPhone number for details:8 800 550 90 72E-mail:info@proftechpol.ru
Financial detailsCurrent account: 40702810870010234730MOSCOW BRANCH OF JSC CB "MODULBANK" MoscowBIC 044525092Correspondent account 30101810645250000092CEO of Nazyrov Anton