CONCRETE FLOOR WITH A HARDENING TOP LAYER AT THE PRODUCTION SITE IN DEDOVSK

WE HAVE SAVED FOR THE CLIENT 505 000
20%Economy
Concrete floor with a hardening top layer at the production facility in Dedovsk

FLOOR ENGINEERING CONSTRUCTION Concrete floor with a hardening top layer at the production facility in Dedovsk

Moscow region, Dedovsk, 1st Volokolamsk street, 78
Characteristics and description
Company name
SM TECHNICS LLC
The purpose of the floor and the room itself
Concrete floor with a hardening top layer at the production facility in Dedovsk
Type of floor
topping floors
Thickness of the concrete layer
12 cm
Room area
753 m²

Customer needs AND THE OPTIMAL ENGINEERING SOLUTION

factors taken into account when developing the floor design

WE HAVE SELECTED THE OPTIMAL ENGINEERING SOLUTION

In November 2023, we already worked with this client and made an industrial floor for a production facility slightly less than 300 m2 in size. And now he has contacted us again, but with a larger task – to complete work on an area of ​​753 m2.

The presence of a concrete base influenced the final technical solution – a concrete floor with a topping of an average thickness of 120 mm was chosen, reinforced with plastic fiber over the entire area, and additionally reinforced with a single layer of reinforcement frame in place of the ramp.

Terms of work
Number of days for all work: 31
Requirements for the quality of work
Floors must comply with SNiP 2.03. 13-88
Appearance of floors
Must look presentable
Durability
Service life of floors without repair (years): 10
Total cost
Budget within the framework of: 2 525 200 ₽
Concrete floor with a hardening top layer at the production facility in Dedovsk: The object before the start of work
The object before the start of work

Floor arrangement ACCORDING TO THE ENGINEERING SOLUTION FOR THE OBJECT: SM TECHNICS LLC

how we implemented this floor design

FEATURES OF THE WORK

According to the contract, we had to dismantle a small section of the floor in front of the gate inside the building in order to make a ramp in this place later. But it so happened that we also removed some of the concrete from the outside of the opening. We had to make a ramp in the originally planned location, and restore the area on the street.

In our opinion, it turned out even better on the street than it was: firstly, we made the new ramp thicker; secondly, we framed it with a metal corner, which was not the case before.

Apart from the large entrance gate, there were no more openings in the room, not even doors. At first, the situation looked like we would be able to fill the entire room in two separate stages. But there was a solution to do this job right away.

In the area of ​​the far wall there was a ladder leading to the mezzanine. The team of grouters went there before the pouring and stayed there until the concrete had hardened sufficiently. And at the right moment they came down and started grouting.

OUR RESULTS

Good work has been done at the facility, resulting in a modern industrial floor with a ramp that meets the expected loads and other requirements.

Stages of implementation engineering design of the floor

engineering design of the floor
1.jpg
Dismantling the place for the ramp
2.jpg
Some of the materials have been accepted
3.jpg
Tamping the base for the ramp inside the room
4.jpg
We are laying the film and gluing the joints
5.jpg
Temperature of the base inside the room
6.jpg
The damping tape has been glued to the columns
7.jpg
The concrete pump on site
8.jpg
During the pouring process, we are leveling the concrete with a laser level
9.jpg
Filling the ramp
10.jpg
After grouting, a moisture-retaining impregnation has been applied to the surface
11.jpg
The seams have been cut
12.jpg
The depth of the seams has been checked

The result of floor engineeringDELIVERED ON TIME, STANDARD, TECHNOLOGICAL INDUSTRIAL FLOORS AT THE FACILITY SM TECHNICS LLC

SEE THE RESULT OF OUR WORK
result-sm-tekhniks.jpg

READ REVIEWS OUR SATISFIED CUSTOMERS

Reviews that we managed to collect between production cycles at our facilities

ReviewsABOUT THE PROFTEHPOL PROJECT

We are well aware that reviews of companies can be very different. Working in the construction market for more than 15 years, we have faced various situations.

We have both satisfied customers and those who are not. But, there is one important thing: we always bring the cycles of our provision to the end. If a client has problems, then we do not leave him with them, but settle them to a full and final conclusion.

Working with us, you can be sure that we will make you an industrial floor that is exactly right for the task for which you needed it.

Thanks to a good knowledge of the technology of industrial floors, we have gathered a lot of practical experience in using floor structures in various difficult places. We solve non-trivial problems and often, when we take an order, 3-4 companies have already tried to take it before us, but refused due to the complexity of the object.

Our clients Which we are proud of

for which we have made good floors
Legal informationSociety Limited Liability "PROFTECHENGINEERING" Shareholdt International consumer society "GOLDEN AXIS"TIN 9709064635CHECKPOINT 770901001OGRN 1207700295406Legal address:109147, Moscow, B.Andronevskaya str., 23, building 1, floor 8, room 4, office of PROFTEHPOL company
POSTAL DETAILSActual address:109147, Moscow, B.Andronevskaya str., 23, building 1, floor 8, room 4, office of PROFTEHPOL companyPhone number for details:8 800 550 90 72E-mail:info@proftechpol.ru
Financial detailsCurrent account: 40702810870010234730MOSCOW BRANCH OF JSC CB "MODULBANK" MoscowBIC 044525092Correspondent account 30101810645250000092CEO of Nazyrov Anton