Our engineering in action
On the example of the floor arrangement for the largest transport and logistics center of Belarus "Prilesye"

INDUSTRIAL FLOOR FOR THE WORKSHOP IN THE VYKHINO METRO AREA

WE HAVE SAVED FOR THE CLIENT 684 800

FLOOR ENGINEERING CONSTRUCTION Concrete floor with a reinforcing top layer for the production shop in Vykhino

Moscow, Kosinskaya str., 9, p. 17
Characteristics and description
Company name
Tandem LLC
The purpose of the floor and the room itself
Concrete floor with a reinforcing top layer for the production shop in Vykhino
Type of floor
topping floors
Thickness of the concrete layer
150 cm
Room area
849 sq. m.

Customer needs AND THE OPTIMAL ENGINEERING SOLUTION

factors taken into account when developing the floor design

WE HAVE SELECTED THE OPTIMAL ENGINEERING SOLUTION

Initially, the customer approached us with a proposal to make a floor according to its design with reinforcement with a dozen fittings, and the fittings at their facility were already connected by area. During the negotiations, we offered our design options and eventually agreed that we would use combined reinforcement – reinforcement + polypropylene fiber.

The loads on the floor in the room were expected to be average. We chose a standard technical solution – a concrete floor with topping.

The following aspects are important to the customer:

Terms of work
Number of days for all work: 14
Requirements for the quality of work
Floors must comply with SNiP 2.03. 13-88
Appearance of floors
Must look presentable
Durability
Service life of floors without repair (years): 10
Total cost
Budget within the framework of: 3 423 900 ₽
Concrete floor with a reinforcing top layer for the production shop in Vykhino: The object before the start of work
The object before the start of work

Floor arrangement ACCORDING TO THE ENGINEERING SOLUTION FOR THE OBJECT: Tandem LLC

how we implemented this floor design

FEATURES OF THE WORKS

For some reason, it turned out that we disassembled and re-connected all the fittings connected in advance by the customer's forces.

It was a pleasure to work with this client, as various unpredictable moments that arose in the course of work were solved immediately. For example, it was planned to fill only one room at first, but the customer suddenly decided to demolish the wall. As a result, we waited until he had completed his part of the work, after which we continued pouring over the entire area. Usually, under such circumstances, the deadlines are greatly stretched, but our customer met in just 2 days.

Due to our technical reasons, we had to postpone the filling for one day during the work. The client was sympathetic to this situation and even offered his own help in solving it.

OUR RESULTS

The customer liked the results of the work. He looked at almost everything after filling and said that he was satisfied with everything. Immediately after the work, payment was made to us without delay.

Stages of implementation engineering design of the floor

engineering design of the floor
1.jpg
Binding of reinforcement
2.jpg
The armature is connected
3.jpg
Preparatory work has been completed
4.jpg
The pump is installed, mixers are on the way
5.jpg
Installed the route
6.jpg
Started filling
7.jpg
Grout stage
8.jpg
A moisture-retaining impregnation was applied
9.jpg
Cutting of shrinkage seams
10.jpg
The seam cutting stage

The result of floor engineeringDELIVERED ON TIME, STANDARD, TECHNOLOGICAL INDUSTRIAL FLOORS AT THE FACILITY Tandem LLC

SEE THE RESULT OF OUR WORK
result-tandem.jpg

READ REVIEWS OUR SATISFIED CUSTOMERS

Reviews that we managed to collect between production cycles at our facilities

ReviewsABOUT THE PROFTEHPOL PROJECT

We are well aware that reviews of companies can be very different. Working in the construction market for more than 15 years, we have faced various situations.

We have both satisfied customers and those who are not. But, there is one important thing: we always bring the cycles of our provision to the end. If a client has problems, then we do not leave him with them, but settle them to a full and final conclusion.

Working with us, you can be sure that we will make you an industrial floor that is exactly right for the task for which you needed it.

Thanks to a good knowledge of the technology of industrial floors, we have gathered a lot of practical experience in using floor structures in various difficult places. We solve non-trivial problems and often, when we take an order, 3-4 companies have already tried to take it before us, but refused due to the complexity of the object.

Our clients Which we are proud of

for which we have made good floors
Legal informationSociety Limited Liability "PROFTECHENGINEERING" Shareholdt International consumer society "GOLDEN AXIS"TIN 9709064635CHECKPOINT 770901001OGRN 1207700295406Legal address:109147, Moscow, B.Andronevskaya str., 23, building 1, floor 8, room 4, office of PROFTEHPOL company
POSTAL DETAILSActual address:109147, Moscow, B.Andronevskaya str., 23, building 1, floor 8, room 4, office of PROFTEHPOL companyPhone number for details:8 800 550 90 72E-mail:info@proftechpol.ru
Financial detailsCurrent account: 40702810870010234730MOSCOW BRANCH OF JSC CB "MODULBANK" MoscowBIC 044525092Correspondent account 30101810645250000092CEO of Nazyrov Anton