WE HAVE SELECTED THE OPTIMAL ENGINEERING SOLUTION
This client contacted us again – a year and a half ago, we already successfully completed work in his repair box. This time, the contract was signed and the advance was paid six months ago, but all this time the customer could not vacate the premises in any way – active production was underway. Finally, during the May holidays, he managed to stop work and transfer the site to us.
The presence of a sufficiently flat concrete base at the facility allowed our chief designer to choose such a technical solution – a concrete floor with an average thickness of 90 mm with a reinforcing top layer, reinforced over the entire area with plastic fiber and additionally reinforced in several small areas with a reinforcing frame.