FEATURES OF THE WORK
The urgency in carrying out the work arose due to the fact that the customer's company was evicted from another rented premises. Therefore, our client quickly found a suitable facility for his production and rented it. But there was a nuance – it was necessary to make a new floor.
Therefore, we had to act extremely quickly. At the beginning of the week, the customer signed and made the payment, and by the end of the same week we had completed the work.
Due to the fact that the premises are rented, there were some difficulties with admission to the facility. In particular, due to the great haste, our team brought the equipment there at 2 a.m. And the client also came to the facility to open it.
Due to the error of the measuring equipment at the stage of measuring the base differences later during pouring, it turned out that the initially laid amount of concrete and, accordingly, fiber was not enough. We have optimally settled this situation with the customer and ordered the required amount of material.
And immediately after the completion of the work at the facility, we spared no money and bought reliable expensive equipment in order to eliminate the factor of inaccuracy of the measuring device in the future.
OUR RESULTS
In a very short time, the client received an industrial floor in a new rented room that meets all production requirements and loads.