WE HAVE SELECTED THE OPTIMAL ENGINEERING SOLUTION
We signed the contract with the client for the floor device back in February 2024, and received an advance payment for the materials at the same time. The building itself did not exist at that time, so we had to wait until spring for the customer to erect walls and make a roof.
The floor had to be made on a sandy base, so the technical solution was approved by the chief designer – a concrete floor with topping reinforced with steel fiber. And the complex of works included the installation of trays in front of the gate inside the room.