Our engineering in action
On the example of the floor arrangement for the largest transport and logistics center of Belarus "Prilesye"

CONCRETE FLOOR FOR THE WORKSHOP AND WAREHOUSE IN THE TVER REGION

WE HAVE SAVED FOR THE CLIENT 280 800

FLOOR ENGINEERING CONSTRUCTION Floor for packing shop and warehouse in Tver region

Tver region, Kimrsky district, Bely Gorodok village, Rechnaya str., 5
Characteristics and description
Company name
OOO"VINT"
The purpose of the floor and the room itself
Floor for packing shop and warehouse in Tver region
Type of floor
topping floors
Thickness of the concrete layer
100 cm
Room area
551.8 m²

Customer needs AND THE OPTIMAL ENGINEERING SOLUTION

factors taken into account when developing the floor design

WE HAVE DETERMINED THE OPTIMAL ENGINEERING SOLUTION

The client needed a strong and durable floor for two rooms – a packing production room and a warehouse. In the first of them, it was necessary to take into account the strength for static loads of 2,000 kg / m2, in the second – for dynamic ones in the form of forklifts with a pallet weighing 600-1000 kg and static ones in the form of 4 pallets with an average weight of 600 kg each.

It was necessary to find an engineering solution suitable for the specifics of the client's work – special detergents and chemicals are used in their production cycle. Various coating options were considered – both polymer and topping. As a result, we opted for a classic solution – a concrete floor with macrofibre with a reinforcing top layer.

Terms of work
Number of days for all work: 30
Requirements for the quality of work
Floors must comply with SNiP 2.03. 13-88
Appearance of floors
Must look presentable
Durability
Service life of floors without repair (years): 5
Total cost
Budget within the framework of: 1 404 000 ₽
Floor for packing shop and warehouse in Tver region: The object before the start of work
The object before the start of work

Floor arrangement ACCORDING TO THE ENGINEERING SOLUTION FOR THE OBJECT: OOO"VINT"

how we implemented this floor design

DIFFICULTIES DURING WORK

There was no concrete node anywhere near the object. During the search, we found several and were already preparing for cooperation, but at the stage of the trip to them and checking, various "shoals" were found, so we continued the search. After putting a lot of effort, we found a suitable node. We went to him, checked (including all legal aspects), and as a result, during the work with the concrete supply, everything was in order.

OUR RESULTS

All stages were completed on time. As a result of the work, the client was satisfied. Separately, he noted the politeness of the workers. For us, this is the first facility in the Tver region. The beginning is laid – more is coming!

Stages of implementation engineering design of the floor

engineering design of the floor
1.jpg
2.jpg
3.jpg
4.jpg
5.jpg
6.jpg

The result of floor engineeringDELIVERED ON TIME, STANDARD, TECHNOLOGICAL INDUSTRIAL FLOORS AT THE FACILITY OOO"VINT"

SEE THE RESULT OF OUR WORK
result-vint.jpg

READ REVIEWS OUR SATISFIED CUSTOMERS

Reviews that we managed to collect between production cycles at our facilities

ReviewsABOUT THE PROFTEHPOL PROJECT

We are well aware that reviews of companies can be very different. Working in the construction market for more than 15 years, we have faced various situations.

We have both satisfied customers and those who are not. But, there is one important thing: we always bring the cycles of our provision to the end. If a client has problems, then we do not leave him with them, but settle them to a full and final conclusion.

Working with us, you can be sure that we will make you an industrial floor that is exactly right for the task for which you needed it.

Thanks to a good knowledge of the technology of industrial floors, we have gathered a lot of practical experience in using floor structures in various difficult places. We solve non-trivial problems and often, when we take an order, 3-4 companies have already tried to take it before us, but refused due to the complexity of the object.

Our clients Which we are proud of

for which we have made good floors
Legal informationSociety Limited Liability "PROFTECHENGINEERING" Shareholdt International consumer society "GOLDEN AXIS"TIN 9709064635CHECKPOINT 770901001OGRN 1207700295406Legal address:109147, Moscow, B.Andronevskaya str., 23, building 1, floor 8, room 4, office of PROFTEHPOL company
POSTAL DETAILSActual address:109147, Moscow, B.Andronevskaya str., 23, building 1, floor 8, room 4, office of PROFTEHPOL companyPhone number for details:8 800 550 90 72E-mail:info@proftechpol.ru
Financial detailsCurrent account: 40702810870010234730MOSCOW BRANCH OF JSC CB "MODULBANK" MoscowBIC 044525092Correspondent account 30101810645250000092CEO of Nazyrov Anton