IDENTIFIED THE MAIN NEEDS OF THE CLIENT
"It is necessary to withstand loads so that a loader with a load can enter it. First, remove the old layer, including the asphalt in front of the gate, and then implement the installation of a new coating," this is how the client formulated the task. Therefore, the floor had to be done in three stages for 4 days each. The technology of laying a fibro-concrete floor with topping was chosen.
The following aspects were important to the customer: