Our engineering in action
On the example of the floor arrangement for the largest transport and logistics center of Belarus "Prilesye"

INDUSTRIAL FLOOR FOR A WAREHOUSE IN THE FILEVSKY PARK AREA

WE HAVE SAVED FOR THE CLIENT 310 300
21%Economy
Floor for the warehouse of LLC "Healthy water", Moscow

FLOOR ENGINEERING CONSTRUCTION Floor for the warehouse of LLC "Healthy water", Moscow

Moscow, Novozavodskaya str., 18, p. 187
Characteristics and description
Company name
LLC "Healthy water"
The purpose of the floor and the room itself
Floor for the warehouse of LLC "Healthy water", Moscow
Type of floor
topping floors
Thickness of the concrete layer
100 cm
Room area
865 sq. m.

Customer needs AND THE OPTIMAL ENGINEERING SOLUTION

factors taken into account when developing the floor design

OBJECT AND CUSTOMER NEEDS

This room was planned as a warehouse with the use of forklifts up to 2.5 tons on rubber wheels. Accordingly, the future floor must comply with SNIP 2.03. 13-88, a flat surface with an error of no more than 4 mm and withstand loads of 3 tons.

The following aspects are important to the customer:

Terms of work
Number of days for all work: 7
Requirements for the quality of work
Floors must comply with SNiP 2.03. 13-88
Appearance of floors
Must look presentable
Durability
Service life of floors without repair (years): 12
Total cost
Budget within the framework of: 1 500 000 ₽
Floor for the warehouse of LLC "Healthy water", Moscow: The object before the start of work
The object before the start of work

Floor arrangement ACCORDING TO THE ENGINEERING SOLUTION FOR THE OBJECT: LLC "Healthy water"

how we implemented this floor design

TECHNOLOGY OF THE DEVICE OF A CONCRETE FLOOR FOR A WAREHOUSE

Having received the consent from the client to conduct a technical assessment, our specialist made all the necessary measurements at the facility and sent it to the technical department of PROFTEHPOL for confirmation.

Based on the data obtained, the chief engineer provided the client with an economical solution for his project, a concrete floor with a 100 mm thick hardener and additionally reinforced with construction micro-reinforcing fiber.

ADVANTAGES OF TECHNOLOGY AND HOW WE MANAGED TO MINIMIZE COSTS

This technology with the use of polypropylene fiber at maximum loads of about 5 tons is ideal both for operation, as it is distributed over the entire thickness of the concrete mixture, and for budget savings, since it excludes a number of works and materials, such as the purchase of reinforcement, binding of reinforcement mesh, purchase of a holder support for reinforcement mesh, and so on.

Thanks to this, we managed to reduce the cost of the project by 27% and save the customer 310,300 rubles.

INSTALLATION OF A FLOOR FOR A WAREHOUSE IN MOSCOW

After signing the contracts and shaking hands, we got to work. We note that the object is typical, of the difficulties we encountered only with sub-zero temperatures at the entrance to the warehouse, where, according to the project, we arranged a large ramp. To solve this problem, we have created a greenhouse at the entrance.

THE RESULT OF OUR WORK

In general, there were no special difficulties at this facility, we successfully passed the facility. The client received a high-quality concrete coating for his needs.

The stages of the floor arrangement and the final result are shown in the photo below.

Stages of implementation engineering design of the floor

engineering design of the floor
1.jpg
Preparation for concrete acceptance
2.jpg
Installation of guiding beacons
3.jpg
Acceptance of concrete mix
4.jpg
Screed concrete with a seven-meter rule
5.jpg
Completion of works on acceptance of concrete mix
6.jpg
Introduction of a hardener by two-rotor machines on disks
7.jpg
Application of a membrane-forming agent
fsZdorovayaVoda.jpg
Cutting of shrinkage seams

The result of floor engineeringDELIVERED ON TIME, STANDARD, TECHNOLOGICAL INDUSTRIAL FLOORS AT THE FACILITY LLC "Healthy water"

SEE THE RESULT OF OUR WORK
result-water.jpg

READ REVIEWS OUR SATISFIED CUSTOMERS

Reviews that we managed to collect between production cycles at our facilities

ReviewsABOUT THE PROFTEHPOL PROJECT

We are well aware that reviews of companies can be very different. Working in the construction market for more than 15 years, we have faced various situations.

We have both satisfied customers and those who are not. But, there is one important thing: we always bring the cycles of our provision to the end. If a client has problems, then we do not leave him with them, but settle them to a full and final conclusion.

Working with us, you can be sure that we will make you an industrial floor that is exactly right for the task for which you needed it.

Thanks to a good knowledge of the technology of industrial floors, we have gathered a lot of practical experience in using floor structures in various difficult places. We solve non-trivial problems and often, when we take an order, 3-4 companies have already tried to take it before us, but refused due to the complexity of the object.

Our clients Which we are proud of

for which we have made good floors
Legal informationSociety Limited Liability "PROFTECHENGINEERING" Shareholdt International consumer society "GOLDEN AXIS"TIN 9709064635CHECKPOINT 770901001OGRN 1207700295406Legal address:109147, Moscow, B.Andronevskaya str., 23, building 1, floor 8, room 4, office of PROFTEHPOL company
POSTAL DETAILSActual address:109147, Moscow, B.Andronevskaya str., 23, building 1, floor 8, room 4, office of PROFTEHPOL companyPhone number for details:8 800 550 90 72E-mail:info@proftechpol.ru
Financial detailsCurrent account: 40702810870010234730MOSCOW BRANCH OF JSC CB "MODULBANK" MoscowBIC 044525092Correspondent account 30101810645250000092CEO of Nazyrov Anton