Our engineering in action
On the example of the floor arrangement for the largest transport and logistics center of Belarus "Prilesye"

INDUSTRIAL FLOOR FOR A WAREHOUSE IN DZERZHINSKY

WE HAVE SAVED FOR THE CLIENT 440 190
29%Economy
Floor for the warehouse of LLC "OLYMP-CITY", MO Dzerzhinsky

FLOOR ENGINEERING CONSTRUCTION Floor for the warehouse of LLC "OLYMP-CITY", MO Dzerzhinsky

MO, Dzerzhinsky, Denisyevsky ave., 3
Characteristics and description
Company name
OLYMP-CITY LLC
The purpose of the floor and the room itself
Floor for the warehouse of LLC "OLYMP-CITY", MO Dzerzhinsky
Type of floor
topping floors
Thickness of the concrete layer
150 cm
Room area
850 sq. m.

Customer needs AND THE OPTIMAL ENGINEERING SOLUTION

factors taken into account when developing the floor design

DESCRIPTION OF THE OBJECT AND THE CLIENT'S NEEDS

The facility was planned as a warehouse for industrial purposes. According to the project, this is a two-storey production building, the client planned to equip a warehouse on the first floor, and arrange the second as a production room. A flat, dust-free concrete floor was required. The room was new, the base consisted of sand and rubble with height differences up to half a meter.

The following aspects are important to the customer:

Terms of work
Number of days for all work: 9
Requirements for the quality of work
Floors must comply with SNiP 2.03. 13-88
Appearance of floors
Must look presentable
Durability
Service life of floors without repair (years): 16
Total cost
Budget within the framework of: 1 500 000 ₽
Floor for the warehouse of LLC "OLYMP-CITY", MO Dzerzhinsky: The object before the start of work
The object before the start of work

Floor arrangement ACCORDING TO THE ENGINEERING SOLUTION FOR THE OBJECT: OLYMP-CITY LLC

how we implemented this floor design

TECHNICAL SOLUTION FOR THIS OBJECT

At this facility, the floor was filled in according to the technical solution of the customer. The loads were planned to be up to 5 tons using a forklift truck. On the second floor there was an overlap with a metal profiled sheet, so it was decided to apply the technology using a double reinforcement mesh.

Fiber-reinforced concrete technology for this object is not suitable in design, since the ceiling would collapse without a metal frame.

HOW WE ARRANGED THE FLOOR IN THE WAREHOUSE

The work was carried out in the spring. Due to the favorable geographical location, the supply of concrete mix was carried out smoothly, which allowed us to complete the floor installation 2 days earlier.

On the ground floor, in some places, the height differences reached 50 centimeters. Access to the second floor was either by a narrow staircase or through an elevator opening. A two-rotor grout machine weighing about 600 kilograms was needed for the area of the second floor with an area of 600 m2.

To solve this problem, we additionally ordered a winch for the object, but since there was no reason to screw the winch with bolts, we decided to weld it to a metal beam. As a result, we successfully lifted the heavy tool to the second floor.

THE RESULT OF OUR WORK

Despite the difficulties of the first floor with a crooked base and the problem of equipment delivery, the work was done efficiently and delivered on time. The client received a ready-to-use warehouse for production purposes.

The stages of the floor arrangement and the final result are shown in the photo below.

Stages of implementation engineering design of the floor

engineering design of the floor
1.jpg
Foundation before the start of work
2.jpg
Concrete supply by concrete truck pump
3.jpg
Acceptance of concrete mix
4.jpg
Screed concrete mix with a seven-meter rule
5.jpg
Completion of concrete acceptance works for the first floor
6.jpg
Finished concrete slab of the first floor
7.jpg
Reception of concrete on the second floor of the warehouse
8.jpg
Completion of the floor installation

The result of floor engineeringDELIVERED ON TIME, STANDARD, TECHNOLOGICAL INDUSTRIAL FLOORS AT THE FACILITY OLYMP-CITY LLC

SEE THE RESULT OF OUR WORK
result-arakel.jpg

READ REVIEWS OUR SATISFIED CUSTOMERS

Reviews that we managed to collect between production cycles at our facilities

ReviewsABOUT THE PROFTEHPOL PROJECT

We are well aware that reviews of companies can be very different. Working in the construction market for more than 15 years, we have faced various situations.

We have both satisfied customers and those who are not. But, there is one important thing: we always bring the cycles of our provision to the end. If a client has problems, then we do not leave him with them, but settle them to a full and final conclusion.

Working with us, you can be sure that we will make you an industrial floor that is exactly right for the task for which you needed it.

Thanks to a good knowledge of the technology of industrial floors, we have gathered a lot of practical experience in using floor structures in various difficult places. We solve non-trivial problems and often, when we take an order, 3-4 companies have already tried to take it before us, but refused due to the complexity of the object.

Our clients Which we are proud of

for which we have made good floors
Legal informationSociety Limited Liability "PROFTECHENGINEERING" Shareholdt International consumer society "GOLDEN AXIS"TIN 9709064635CHECKPOINT 770901001OGRN 1207700295406Legal address:109147, Moscow, B.Andronevskaya str., 23, building 1, floor 8, room 4, office of PROFTEHPOL company
POSTAL DETAILSActual address:109147, Moscow, B.Andronevskaya str., 23, building 1, floor 8, room 4, office of PROFTEHPOL companyPhone number for details:8 800 550 90 72E-mail:info@proftechpol.ru
Financial detailsCurrent account: 40702810870010234730MOSCOW BRANCH OF JSC CB "MODULBANK" MoscowBIC 044525092Correspondent account 30101810645250000092CEO of Nazyrov Anton