Our engineering in action
On the example of the floor arrangement for the largest transport and logistics center of Belarus "Prilesye"

THE FOUNDATION AND THE FLOOR AT THE SAME TIME FOR A PREFABRICATED BUILDING IN THE MOSCOW REGION

WE HAVE SAVED FOR THE CLIENT 1 468 500
20%Economy
Foundation plate and floor for a prefabricated building in the Moscow region

FLOOR ENGINEERING CONSTRUCTION Foundation plate and floor for a prefabricated building in the Moscow region

50 Borisovo village, Dmitrovsky district, Moscow region
Characteristics and description
Company name
Rintrade LLC
The purpose of the floor and the room itself
Foundation plate and floor for a prefabricated building in the Moscow region
Type of floor
topping floors
Thickness of the concrete layer
20 cm
Room area
971.5 m²

Customer needs AND THE OPTIMAL ENGINEERING SOLUTION

factors taken into account when developing the floor design

WE HAVE SELECTED THE OPTIMAL ENGINEERING SOLUTION

At this facility, it was necessary to perform not just an industrial floor – the task was to implement a foundation plate for a prefabricated building.

The uniqueness of the design consisted in combining three different components – the foundation, the floor and the finish coating – into a single whole. Speaking in more technical terms, the engineering solution was chosen as follows – a seamless foundation plate, which is simultaneously a floor with a reinforced top layer.

This technology has significantly reduced time and money costs.

Terms of work
Number of days for all work: 17
Requirements for the quality of work
Floors must comply with SNiP 2.03. 13-88
Appearance of floors
Must look presentable
Durability
Service life of floors without repair (years): 10
Total cost
Budget within the framework of: 7 342 700 ₽
Foundation plate and floor for a prefabricated building in the Moscow region: The object before the start of work
The object before the start of work

Floor arrangement ACCORDING TO THE ENGINEERING SOLUTION FOR THE OBJECT: Rintrade LLC

how we implemented this floor design

FEATURES OF THE WORK

Before the work on the concrete slab, we still had to turn the site with untreated soil, debris and pieces of old concrete slabs into a proper sandy base. A large crawler excavator and an ice rink were involved.

A surveyor was called to determine the correct shape and exact boundaries of the future plate.

One of the factors of a significant reduction in the budget and work time is combined reinforcement. Instead of a double layer of reinforcement, we used a single layer in combination with steel fiber.

The reinforcement cage on this object was located not as usual at the bottom on the clamps, but in the upper part of the plate. We did not just make a floor, but also a foundation, and one of the functions of reinforcement was to provide resistance to wind loads that would be transmitted from the building.

During the course of the work, the customer was worried about the risk of not being able to finish the work before the onset of rains and low temperatures. We calmed him down in every possible way, demonstrating competence and performing each step as quickly as possible.

Unfortunately, there were some minor comments. There was a fiber sticking out on the surface of the slab in some places. We carefully removed it, and patched up the dimples.

OUR RESULTS

Thanks to the cooperation with our company, the customer received three products in one at once: the foundation, the floor, and the finish coating.

Stages of implementation engineering design of the floor

engineering design of the floor
1.jpg
Removing old concrete slabs
2.jpg
Digging the foundation to the desired level
3.jpg
Pegs have been placed along the boundaries of the pit
4.jpg
Non-removable formwork has been installed
5.jpg
Reinforcement has been installed
6.jpg
Checking the upper protective layer above the reinforcement
7.jpg
The site is ready for pouring
8.jpg
Pouring is in progress
9.jpg
Compacting the concrete with a vibrating beam
10.jpg
Leveling the concrete using a laser level
11.jpg
Pouring has been finished
12.jpg
Applying varnish

The result of floor engineeringDELIVERED ON TIME, STANDARD, TECHNOLOGICAL INDUSTRIAL FLOORS AT THE FACILITY Rintrade LLC

SEE THE RESULT OF OUR WORK
result-rintrejd-borisovo.jpg

READ REVIEWS OUR SATISFIED CUSTOMERS

Reviews that we managed to collect between production cycles at our facilities

ReviewsABOUT THE PROFTEHPOL PROJECT

We are well aware that reviews of companies can be very different. Working in the construction market for more than 15 years, we have faced various situations.

We have both satisfied customers and those who are not. But, there is one important thing: we always bring the cycles of our provision to the end. If a client has problems, then we do not leave him with them, but settle them to a full and final conclusion.

Working with us, you can be sure that we will make you an industrial floor that is exactly right for the task for which you needed it.

Thanks to a good knowledge of the technology of industrial floors, we have gathered a lot of practical experience in using floor structures in various difficult places. We solve non-trivial problems and often, when we take an order, 3-4 companies have already tried to take it before us, but refused due to the complexity of the object.

Our clients Which we are proud of

for which we have made good floors
Legal informationSociety Limited Liability "PROFTECHENGINEERING" Shareholdt International consumer society "GOLDEN AXIS"TIN 9709064635CHECKPOINT 770901001OGRN 1207700295406Legal address:109147, Moscow, B.Andronevskaya str., 23, building 1, floor 8, room 4, office of PROFTEHPOL company
POSTAL DETAILSActual address:109147, Moscow, B.Andronevskaya str., 23, building 1, floor 8, room 4, office of PROFTEHPOL companyPhone number for details:8 800 550 90 72E-mail:info@proftechpol.ru
Financial detailsCurrent account: 40702810870010234730MOSCOW BRANCH OF JSC CB "MODULBANK" MoscowBIC 044525092Correspondent account 30101810645250000092CEO of Nazyrov Anton