Our engineering in action
On the example of the floor arrangement for the largest transport and logistics center of Belarus "Prilesye"

CONCRETE FLOOR WITH TOPPING IN THE GOROD SHOPPING CENTER IN KOSINO MOSCOW

WE HAVE SAVED FOR THE CLIENT 235 300

FLOOR ENGINEERING CONSTRUCTION Industrial floor for the administrative premises of the shopping mall City of Moscow

Moscow, Novoukhtomskoe highway, vl. 2A, shopping center "Gorod" Kosino
Characteristics and description
Company name
LLC "TRASKO-INVEST"
The purpose of the floor and the room itself
Industrial floor for the administrative premises of the shopping mall City of Moscow
Type of floor
topping floors
Thickness of the concrete layer
150 cm
Room area
594.19 m²

Customer needs AND THE OPTIMAL ENGINEERING SOLUTION

factors taken into account when developing the floor design

FOUND OUT THE NEEDS OF THE CLIENT

This time our customer was a Polish company. If we also take into account that Globus is a German brand, then our entire project at this facility can be safely called international. The customer needed a ready-made concrete floor as soon as possible. To be more specific, on Monday we had just started negotiating, and next week we had to install refrigerators. There was no time from the word "absolutely". The contract was signed as quickly as possible. On Friday, the advance payment came, and it was agreed that we should start work from Saturday. We had only 5 days for the whole project.

The following aspects are important to the customer:

Terms of work
Number of days for all work: 5
Requirements for the quality of work
Floors must comply with SNiP 2.03. 13-88
Appearance of floors
Must look presentable
Durability
Service life of floors without repair (years): 20
Total cost
Budget within the framework of: 2 353 000 ₽
Industrial floor for the administrative premises of the shopping mall City of Moscow: The object before the start of work
The object before the start of work

Floor arrangement ACCORDING TO THE ENGINEERING SOLUTION FOR THE OBJECT: LLC "TRASKO-INVEST"

how we implemented this floor design

DIFFICULTIES DURING WORK

As mentioned above, the main difficulty at this facility was the time factor. We usually carry out such projects within 7 days, and the supply department takes 5 days to prepare. And here, because of too tight deadlines, we had to act lightning fast at every stage.

In addition to the lack of time, there was another point that caused difficulties – the object itself is non-standard. When filling the basement on the ground floor, we laid a very long concrete pump track (about 100 meters). The corridor also had its own peculiarities – 40 meters long, with many turns, which is why it was constantly necessary to disassemble and re-mount the track.

At one of the sites, the thickness of the floor was only about 40 mm, which contradicted the standard technology, but it was worth considering that it was not possible to do something differently in this online store. As in other rooms, there also had to be a floor with topping. The foundation slab acted as concrete – of course, it was impossible to dismantle. It was also impossible to raise the floor mark, since it was connected to all other rooms. A non–standard solution was chosen - 40 mm of concrete with a hardener was glued to the base. The adhesive was made of a special material, this adhesive was applied during concreting. Thus, this section was made together with all the other sections of the topping, where the thickness was standard.

OUR RESULTS

Despite the high price that we announced for the customer, he agreed to cooperate with us. And we did not disappoint – we completed the entire scope of work as standard and within the agreed time frame. The customer was very satisfied.

Stages of implementation engineering design of the floor

engineering design of the floor
1.jpg
They brought the profile and the grid
2.jpg
A concrete pump is approaching
3.jpg
We have completed filling in one of the sections
4.jpg
Taking measurements
5.jpg
The reinforcement units at the columns are ready
6.jpg
The object is ready for the second fill
7.jpg
Installation of the route
8.jpg
Finishing the installation of the route
9.jpg
The mixer has arrived
10.jpg
We accept and level the concrete mixture
11.jpg
Teamwork on leveling the concrete layer
12.jpg
Completing the fill
13.jpg
Concrete processing has begun
14.jpg
Rail control
15.jpg
Topping is applied to the surface
16.jpg
Transition to 10 mm from the topping under the tiling

The result of floor engineeringDELIVERED ON TIME, STANDARD, TECHNOLOGICAL INDUSTRIAL FLOORS AT THE FACILITY LLC "TRASKO-INVEST"

SEE THE RESULT OF OUR WORK
result-trasko-invest.jpg

READ REVIEWS OUR SATISFIED CUSTOMERS

Reviews that we managed to collect between production cycles at our facilities

ReviewsABOUT THE PROFTEHPOL PROJECT

We are well aware that reviews of companies can be very different. Working in the construction market for more than 15 years, we have faced various situations.

We have both satisfied customers and those who are not. But, there is one important thing: we always bring the cycles of our provision to the end. If a client has problems, then we do not leave him with them, but settle them to a full and final conclusion.

Working with us, you can be sure that we will make you an industrial floor that is exactly right for the task for which you needed it.

Thanks to a good knowledge of the technology of industrial floors, we have gathered a lot of practical experience in using floor structures in various difficult places. We solve non-trivial problems and often, when we take an order, 3-4 companies have already tried to take it before us, but refused due to the complexity of the object.

Our clients Which we are proud of

for which we have made good floors
Legal informationSociety Limited Liability "PROFTECHENGINEERING" Shareholdt International consumer society "GOLDEN AXIS"TIN 9709064635CHECKPOINT 770901001OGRN 1207700295406Legal address:109147, Moscow, B.Andronevskaya str., 23, building 1, floor 8, room 4, office of PROFTEHPOL company
POSTAL DETAILSActual address:109147, Moscow, B.Andronevskaya str., 23, building 1, floor 8, room 4, office of PROFTEHPOL companyPhone number for details:8 800 550 90 72E-mail:info@proftechpol.ru
Financial detailsCurrent account: 40702810870010234730MOSCOW BRANCH OF JSC CB "MODULBANK" MoscowBIC 044525092Correspondent account 30101810645250000092CEO of Nazyrov Anton