WE HAVE SELECTED THE OPTIMAL ENGINEERING SOLUTION
This time, the customer came to us with a task that was not quite standard for us. The parking lot's floor slab had a damaged protective layer. We needed to restore it and simultaneously pour the floor.
The technical solution was selected accordingly: dismantling the old base and applying an adhesive compound; then, installing a hardened concrete floor with an average thickness of 110 mm and a combined reinforcement of a frame and plastic fiber.