Our engineering in action
On the example of the floor arrangement for the largest transport and logistics center of Belarus "Prilesye"

THE FIRST FLOOR SLAB CONSTRUCTION IN RUSSIA WHICH IS THE FOUNDATION AND FLOOR AT THE SAME TIME FOR A WAREHOUSE IN ALANYA

FLOOR ENGINEERING CONSTRUCTION The unique design of the floor plate – the foundation and the floor at the same time for the warehouse of LLC GC PD "Bavaria", Vladikavkaz

Vladikavkaz, Telman str., 45
Characteristics and description
Company name
LLC GC PD "Bavaria"
The purpose of the floor and the room itself
The unique design of the floor plate – the foundation and the floor at the same time for the warehouse of LLC GC PD "Bavaria", Vladikavkaz
Type of floor
topping floors

Customer needs AND THE OPTIMAL ENGINEERING SOLUTION

factors taken into account when developing the floor design

FLOOR DESIGN REQUIREMENTS

The main requirement for the bearing capacity of the foundation plate was the condition that the concentrated load would be at least 8.5 tons per rack support.
Also, the foundation plate should combine the characteristics of an industrial floor.
In addition, the mark of the top of the foundation plate should be 1.2 m above ground level.

WHO WAS OUR CLIENT

The Bavaria Group of companies in Vladikavkaz is engaged in the production of beer and soft drinks, the development and cultivation of seeds for agriculture and the cultivation of agricultural products, and they have restaurants in Vladikavkaz. She is very famous, participates in international exhibitions. The current founder of the company is the head of the Republic of North Ossetia.

HOW WE STARTED OUR COOPERATION

We were recommended to the client by our partner – the company Stelkon, which is engaged in self-supporting warehouses. It was very interesting for them to try steel fiber reinforced structures, and we are great experts in this.

Terms of work
Number of days for all work: null
Requirements for the quality of work
Floors must comply with SNiP 2.03. 13-88
Appearance of floors
Must look presentable

Floor arrangement ACCORDING TO THE ENGINEERING SOLUTION FOR THE OBJECT: LLC GC PD "Bavaria"

how we implemented this floor design

STEEL-FIBER CONCRETE SLAB WITH REINFORCED TOP LAYER FOR THE WAREHOUSE OF THE BAVARIA GROUP OF COMPANIES

THE UNIQUENESS OF THIS PROJECT

This technology was applied in Russia for the first time, and we did it! That is, for the first time we performed the technology of the plate device, which simultaneously performs the functions of a foundation for a self-supporting warehouse and a floor. In this design, the shelving system is simultaneously the supporting frame of the warehouse, on which the enclosing walls and roof are attached.

samonesuschiy-sklad.jpg

Construction of a self-supporting warehouse

So, we have started designing a modern warehouse of 1900 m2 for storing finished products. It must have the maximum filling of the goods and a high speed of work. Therefore, a system of shelving with filling using shuttles (robots that move goods around the warehouse themselves) was chosen. This is a modern type of warehouses – the most modern among those that the company has.

A NEW TYPE OF SOLUTION

The standard solution for such conditions was previously a foundation plate, where a frame of reinforcing rods acted as reinforcement. We turned to our partners, namely the Belgian company Beckart (the world leader in the production of steel fiber) with a request to develop a foundation plate in which steel fiber would act as reinforcement.

Beckart has extensive experience in using similar structures in Europe. Therefore, a standard solution was proposed, but with one exception – taking into account the temperature conditions, in addition to the steel fiber, a reinforcement mesh made of reinforcement with a diameter of 10 mm was designed, located in the upper part of the plate.

OUR ROLE IN THE PROJECT

Our service consisted not only in the direct production of work on the production of the plate, but also in the following:

In the design of the foundation plate itself;

And also in the design of a retaining wall, with the help of which the foundation plate will be held in space + 1 meter above ground level.

The company Beckart provided us with a calculation based on the designed structure, which was developed by our company in accordance with the construction standards of the Russian Federation.

schema.png

Part of the self-supporting warehouse project

THE DIFFICULTIES WE FACED

When selecting the composition of concrete, it was necessary to take into account the specifics of local bulk materials (sand and crushed stone). As a result, the optimal water-cement ratio was selected during the production process at the beginning of concreting.
Weather conditions – it was March outside and there was no stable sunny weather, i.e. hot days were replaced by rains. The slab was poured in 4 stages, but each stage had to be carried out without stopping. Therefore, the floor slab was protected from both the sun and moisture.
Since the concrete had to be taken with the help of a concrete pump, the largest concrete pump in the whole of North Ossetia was involved for this task. This solution turned out to be optimal due to the great remoteness of some sections of the plate.
Our company's base is located in Moscow, while the facility itself is in Vladikavkaz. This factor required us to monitor suppliers of concrete, materials, taking into account the peculiarities of the local climate, since the production of a plate with a hardener (topping) was carried out in the open air.

THE RESULT OF OUR WORK

As a result, the client received a foundation plate together with a floor covering that meets all its operational requirements in a very short period of time and with a significant reduction in costs compared to standard solutions. This is a two-fold saving.

For our part, we would like to express our sincere gratitude for the comprehensive support of the customer's service; for assistance in organizing the process and ensuring constant financing; the highest possible speed in solving any working issues.

We love such projects that raise our competence to a new level. We had the courage and skill to implement this new solution. After all , we had to:

  1. To study the local concrete market, as this is one of the main components of success in the production of floors;
  2. To select qualified personnel;
  3. To study the design features of foundation slabs made of steel fiber, since before that steel fiber was used only for the design of floors;
  4. To provide logistics, because the object is 1000 km from Moscow.

WHERE ELSE CAN SUCH SOLUTIONS BE APPLIED

This technology is suitable for:

  • All clients who are engaged in the construction and operation of modern warehouse buildings;
  • For those who are building for the purpose of renting or selling;
  • Large producers of products who need to store products somewhere and who set the task of maximizing the use of production space;
  • Designers and design organizations that design warehouse facilities;
  • Large general contracting organizations that are engaged in the construction of large industrial facilities, where a warehouse is part of the construction.

Stages of implementation engineering design of the floor

engineering design of the floor
1.jpg
2.jpg
3.jpg
4.jpg
5.jpg
6.jpg
7.jpg
8.jpg
9.jpg
10.jpg
11.jpg
12.jpg
14.jpg

The result of floor engineeringDELIVERED ON TIME, STANDARD, TECHNOLOGICAL INDUSTRIAL FLOORS AT THE FACILITY LLC GC PD "Bavaria"

SEE THE RESULT OF OUR WORK
result-bavariya.jpg

READ REVIEWS OUR SATISFIED CUSTOMERS

Reviews that we managed to collect between production cycles at our facilities

ReviewsABOUT THE PROFTEHPOL PROJECT

We are well aware that reviews of companies can be very different. Working in the construction market for more than 15 years, we have faced various situations.

We have both satisfied customers and those who are not. But, there is one important thing: we always bring the cycles of our provision to the end. If a client has problems, then we do not leave him with them, but settle them to a full and final conclusion.

Working with us, you can be sure that we will make you an industrial floor that is exactly right for the task for which you needed it.

Thanks to a good knowledge of the technology of industrial floors, we have gathered a lot of practical experience in using floor structures in various difficult places. We solve non-trivial problems and often, when we take an order, 3-4 companies have already tried to take it before us, but refused due to the complexity of the object.

Our clients Which we are proud of

for which we have made good floors
Legal informationSociety Limited Liability "PROFTECHENGINEERING" Shareholdt International consumer society "GOLDEN AXIS"TIN 9709064635CHECKPOINT 770901001OGRN 1207700295406Legal address:109147, Moscow, B.Andronevskaya str., 23, building 1, floor 8, room 4, office of PROFTEHPOL company
POSTAL DETAILSActual address:109147, Moscow, B.Andronevskaya str., 23, building 1, floor 8, room 4, office of PROFTEHPOL companyPhone number for details:8 800 550 90 72E-mail:info@proftechpol.ru
Financial detailsCurrent account: 40702810870010234730MOSCOW BRANCH OF JSC CB "MODULBANK" MoscowBIC 044525092Correspondent account 30101810645250000092CEO of Nazyrov Anton