Our engineering in action
On the example of the floor arrangement for the largest transport and logistics center of Belarus "Prilesye"

TOPPING FLOOR FOR A WAREHOUSE IN THE MOSCOW REGION

WE HAVE SAVED FOR THE CLIENT 506 100
20%Economy
Topping concrete floor for a warehouse in the Andreevskoye Industrial Park

FLOOR ENGINEERING CONSTRUCTION Topping concrete floor for a warehouse in the Andreevskoye Industrial Park

Moscow region, Leninsky district, Andreevskoye village, Andreevskoye Industrial Park, p. 16B
Characteristics and description
Company name
ALLGOI LLC
The purpose of the floor and the room itself
Topping concrete floor for a warehouse in the Andreevskoye Industrial Park
Type of floor
topping floors
Thickness of the concrete layer
9 cm
Room area
879 m²

Customer needs AND THE OPTIMAL ENGINEERING SOLUTION

factors taken into account when developing the floor design

WE HAVE SELECTED THE OPTIMAL ENGINEERING SOLUTION

The customer of the work was the tenant of the production and warehouse building. It was necessary to make a concrete floor on the ground floor.

The current base was old concrete, so a classic technical solution was chosen for such a case – a topping floor with an average thickness of 90 mm, reinforced with plastic fiber.

Terms of work
Number of days for all work: 5
Requirements for the quality of work
Floors must comply with SNiP 2.03. 13-88
Appearance of floors
Must look presentable
Durability
Service life of floors without repair (years): 10
Total cost
Budget within the framework of: 2 530 600 ₽
Topping concrete floor for a warehouse in the Andreevskoye Industrial Park: The object before the start of work
The object before the start of work

Floor arrangement ACCORDING TO THE ENGINEERING SOLUTION FOR THE OBJECT: ALLGOI LLC

how we implemented this floor design

FEATURES OF THE WORK

nitially, the customer and I, in addition to the actual manufacture of the floor, planned to install three more ramps. To do this, it would have been necessary to dismantle the base in front of the gate, but the building owner did not allow it. Therefore, this part of the work was canceled.

After work in some places, the topping peeled off. We repaired these areas twice: first with one composition, but the customer did not like it, because it did not match in color; the second time we used a different composition, and then it turned out better.

OUR RESULTS

Yes, the work at this facility was not without flaws. But we eliminated them and eventually transferred the floor with the declared production parameters to the client for use.

Stages of implementation engineering design of the floor

engineering design of the floor
1.jpg
Film, damper tape and macrofibre and on-site
2.jpg
The team delivered the equipment to the facility
3.jpg
The customer has freed up the space for filling
4.jpg
We are laying the film
5.jpg
Preparation is being completed
6.jpg
As an insulating seam, we glue a damping tape along the walls
7.jpg
Topping on site
8.jpg
The concrete pump has arrived
9.jpg
Fiber on the concrete node
10.jpg
The filling has started
11.jpg
Completed the filling
12.jpg
Grout
13.jpg
After grouting, a membrane forming agent (varnish) was applied
14.jpg
Cutting seams
15.jpg
The seams are cut
16.jpg
Sealed seams

The result of floor engineeringDELIVERED ON TIME, STANDARD, TECHNOLOGICAL INDUSTRIAL FLOORS AT THE FACILITY ALLGOI LLC

SEE THE RESULT OF OUR WORK
result-allgoy-industrialnyj-park-andreevskoe.jpg

READ REVIEWS OUR SATISFIED CUSTOMERS

Reviews that we managed to collect between production cycles at our facilities

ReviewsABOUT THE PROFTEHPOL PROJECT

We are well aware that reviews of companies can be very different. Working in the construction market for more than 15 years, we have faced various situations.

We have both satisfied customers and those who are not. But, there is one important thing: we always bring the cycles of our provision to the end. If a client has problems, then we do not leave him with them, but settle them to a full and final conclusion.

Working with us, you can be sure that we will make you an industrial floor that is exactly right for the task for which you needed it.

Thanks to a good knowledge of the technology of industrial floors, we have gathered a lot of practical experience in using floor structures in various difficult places. We solve non-trivial problems and often, when we take an order, 3-4 companies have already tried to take it before us, but refused due to the complexity of the object.

Our clients Which we are proud of

for which we have made good floors
Legal informationSociety Limited Liability "PROFTECHENGINEERING" Shareholdt International consumer society "GOLDEN AXIS"TIN 9709064635CHECKPOINT 770901001OGRN 1207700295406Legal address:109147, Moscow, B.Andronevskaya str., 23, building 1, floor 8, room 4, office of PROFTEHPOL company
POSTAL DETAILSActual address:109147, Moscow, B.Andronevskaya str., 23, building 1, floor 8, room 4, office of PROFTEHPOL companyPhone number for details:8 800 550 90 72E-mail:info@proftechpol.ru
Financial detailsCurrent account: 40702810870010234730MOSCOW BRANCH OF JSC CB "MODULBANK" MoscowBIC 044525092Correspondent account 30101810645250000092CEO of Nazyrov Anton