WE HAVE SELECTED THE OPTIMAL ENGINEERING SOLUTION
At this facility, the task was to make a floor for a building that did not exist yet. The customer planned to build a prefabricated warehouse on our already finished floor by another contractor. Therefore, the scope of work included preparing a base of sand and filling the floor even in street conditions.
A standard technical solution was chosen – a concrete floor with topping. But the thickness was already required seriously – 200 mm – for the reason described above. According to the project, 2 layers of reinforcement were to be connected, and additional reinforcement was required along the perimeter, where the largest load from the building falls.
The following aspects are important to the customer: