TOPPING FLOOR FOR A PREFABRICATED WAREHOUSE IN MYTISHCHI

WE HAVE SAVED FOR THE CLIENT 315 600
20%Economy
Topping floor for a prefabricated warehouse in Mytishchi

FLOOR ENGINEERING CONSTRUCTION Topping floor for a prefabricated warehouse in Mytishchi

MO, Mytishchi, Abramova str., 11
Characteristics and description
Company name
VITAND COMPANY LLC
The purpose of the floor and the room itself
Topping floor for a prefabricated warehouse in Mytishchi
Type of floor
topping floors
Thickness of the concrete layer
200 cm
Room area
217 sq. m.

Customer needs AND THE OPTIMAL ENGINEERING SOLUTION

factors taken into account when developing the floor design

WE HAVE SELECTED THE OPTIMAL ENGINEERING SOLUTION

At this facility, the task was to make a floor for a building that did not exist yet. The customer planned to build a prefabricated warehouse on our already finished floor by another contractor. Therefore, the scope of work included preparing a base of sand and filling the floor even in street conditions.

A standard technical solution was chosen – a concrete floor with topping. But the thickness was already required seriously – 200 mm – for the reason described above. According to the project, 2 layers of reinforcement were to be connected, and additional reinforcement was required along the perimeter, where the largest load from the building falls.

The following aspects are important to the customer:

Terms of work
Number of days for all work: 14
Requirements for the quality of work
Floors must comply with SNiP 2.03. 13-88
Appearance of floors
Must look presentable
Durability
Service life of floors without repair (years): 10
Total cost
Budget within the framework of: 1 578 100 ₽
Topping floor for a prefabricated warehouse in Mytishchi: The object before the start of work
The object before the start of work

Floor arrangement ACCORDING TO THE ENGINEERING SOLUTION FOR THE OBJECT: VITAND COMPANY LLC

how we implemented this floor design

FEATURES OF THE WORKS

Before the pouring stage, we arranged the base of sand on our own, which was provided to us by the customer.

After the main work and cutting the seams, we did not seal them for a long time, because the object was still on the street, and the necessary condition for the quality of the final step is the dryness of the shrinkage seams. Therefore, we were able to finish the work completely when the building was already fully built.

OUR RESULTS

The client received on time a high-quality coating for the warehouse, where the racks have already been installed and which is already in full operation.

Stages of implementation engineering design of the floor

engineering design of the floor
1.jpg
Preparation of the foundation
2.jpg
Preparing the foundation
3.jpg
The stage with the foundation is completed
4.jpg
Reinforcement is being performed
5.jpg
Bottom layer of the grid
6.jpg
The damper tape is glued
7.jpg
The filling stage has begun
8.jpg
Filling stage
9.jpg
Filling is being completed
10.jpg
Finished leveling the concrete
11.jpg
Applied topping
12.jpg
Moisture-retaining impregnation is applied

The result of floor engineeringDELIVERED ON TIME, STANDARD, TECHNOLOGICAL INDUSTRIAL FLOORS AT THE FACILITY VITAND COMPANY LLC

SEE THE RESULT OF OUR WORK
result-vitand.jpg

READ REVIEWS OUR SATISFIED CUSTOMERS

Reviews that we managed to collect between production cycles at our facilities

ReviewsABOUT THE PROFTEHPOL PROJECT

We are well aware that reviews of companies can be very different. Working in the construction market for more than 15 years, we have faced various situations.

We have both satisfied customers and those who are not. But, there is one important thing: we always bring the cycles of our provision to the end. If a client has problems, then we do not leave him with them, but settle them to a full and final conclusion.

Working with us, you can be sure that we will make you an industrial floor that is exactly right for the task for which you needed it.

Thanks to a good knowledge of the technology of industrial floors, we have gathered a lot of practical experience in using floor structures in various difficult places. We solve non-trivial problems and often, when we take an order, 3-4 companies have already tried to take it before us, but refused due to the complexity of the object.

Our clients Which we are proud of

for which we have made good floors
Legal informationSociety Limited Liability "PROFTECHENGINEERING" Shareholdt International consumer society "GOLDEN AXIS"TIN 9709064635CHECKPOINT 770901001OGRN 1207700295406Legal address:109147, Moscow, B.Andronevskaya str., 23, building 1, floor 8, room 4, office of PROFTEHPOL company
POSTAL DETAILSActual address:109147, Moscow, B.Andronevskaya str., 23, building 1, floor 8, room 4, office of PROFTEHPOL companyPhone number for details:8 800 550 90 72E-mail:info@proftechpol.ru
Financial detailsCurrent account: 40702810870010234730MOSCOW BRANCH OF JSC CB "MODULBANK" MoscowBIC 044525092Correspondent account 30101810645250000092CEO of Nazyrov Anton