Our engineering in action
On the example of the floor arrangement for the largest transport and logistics center of Belarus "Prilesye"

CONCRETE FLOOR WITH TOPPING FOR A GARAGE IN THE PUSHKIN DISTRICT

WE HAVE SAVED FOR THE CLIENT 487 400
20%Economy
Topping floor for auto garage in the village of Lesnye Polyany

FLOOR ENGINEERING CONSTRUCTION Topping floor for auto garage in the village of Lesnye Polyany

MO, G.O. Pushkinsky, village Forest Glades, Novaya str., p. 7A
Characteristics and description
Company name
LLC "Pushkinskaya GRS"
The purpose of the floor and the room itself
Topping floor for auto garage in the village of Lesnye Polyany
Type of floor
topping floors
Thickness of the concrete layer
150 cm
Room area
625 sq. m.

Customer needs AND THE OPTIMAL ENGINEERING SOLUTION

factors taken into account when developing the floor design

WE HAVE DETERMINED THE OPTIMAL ENGINEERING SOLUTION

The room is a former garage. It was necessary to convert it into a warehouse with a flat floor, on which racks would later be installed. Everything was ready for the work. It remained to agree on the price, after which it was possible to get down to business right away. The customer called evenness and strength the most important qualities for the final coating.

The technical solution proposed by us and subsequently implemented is a concrete floor with macrofibre and topping.

The following aspects are important to the customer:

Terms of work
Number of days for all work: 30
Requirements for the quality of work
Floors must comply with SNiP 2.03. 13-88
Appearance of floors
Must look presentable
Durability
Service life of floors without repair (years): 5
Total cost
Budget within the framework of: 2 437 000 ₽
Topping floor for auto garage in the village of Lesnye Polyany: The object before the start of work
The object before the start of work

Floor arrangement ACCORDING TO THE ENGINEERING SOLUTION FOR THE OBJECT: LLC "Pushkinskaya GRS"

how we implemented this floor design

DIFFICULTIES DURING WORK

The client wanted to save as much as possible. The base was uneven. Fulfilling his wish, we made a small slope, repeating the base, in order to reduce the consumption of concrete.

OUR RESULTS

The work was completed on time and in accordance with the chosen engineering solution. We also fulfilled another customer's wish and framed two ramps with corners. He was satisfied with this and the overall result of the work.

Stages of implementation engineering design of the floor

engineering design of the floor
1.jpg
Delivery of material to the facility
2.jpg
Ramp preparation
3.jpg
The ramp is framed with corners and reinforced
4.jpg
Preparing the room for filling
5.jpg
The concrete pump has arrived. Laying of a route for concrete supply
6.jpg
We accept and level the concrete mixture indoors
7.jpg
The concrete layer on the ramp was taken and leveled
8.jpg
Coating treatment with grout machines
9.jpg
A moisture-retaining impregnation was applied
10.jpg
The stage of cutting shrinkage seams

The result of floor engineeringDELIVERED ON TIME, STANDARD, TECHNOLOGICAL INDUSTRIAL FLOORS AT THE FACILITY LLC "Pushkinskaya GRS"

SEE THE RESULT OF OUR WORK
result-puskinskaya-grs.jpg

READ REVIEWS OUR SATISFIED CUSTOMERS

Reviews that we managed to collect between production cycles at our facilities

ReviewsABOUT THE PROFTEHPOL PROJECT

We are well aware that reviews of companies can be very different. Working in the construction market for more than 15 years, we have faced various situations.

We have both satisfied customers and those who are not. But, there is one important thing: we always bring the cycles of our provision to the end. If a client has problems, then we do not leave him with them, but settle them to a full and final conclusion.

Working with us, you can be sure that we will make you an industrial floor that is exactly right for the task for which you needed it.

Thanks to a good knowledge of the technology of industrial floors, we have gathered a lot of practical experience in using floor structures in various difficult places. We solve non-trivial problems and often, when we take an order, 3-4 companies have already tried to take it before us, but refused due to the complexity of the object.

Our clients Which we are proud of

for which we have made good floors
Legal informationSociety Limited Liability "PROFTECHENGINEERING" Shareholdt International consumer society "GOLDEN AXIS"TIN 9709064635CHECKPOINT 770901001OGRN 1207700295406Legal address:109147, Moscow, B.Andronevskaya str., 23, building 1, floor 8, room 4, office of PROFTEHPOL company
POSTAL DETAILSActual address:109147, Moscow, B.Andronevskaya str., 23, building 1, floor 8, room 4, office of PROFTEHPOL companyPhone number for details:8 800 550 90 72E-mail:info@proftechpol.ru
Financial detailsCurrent account: 40702810870010234730MOSCOW BRANCH OF JSC CB "MODULBANK" MoscowBIC 044525092Correspondent account 30101810645250000092CEO of Nazyrov Anton