Our engineering in action
On the example of the floor arrangement for the largest transport and logistics center of Belarus "Prilesye"

INDUSTRIAL FLOOR FOR THE WORKSHOP IN THE KALUGA REGION

WE HAVE SAVED FOR THE CLIENT 121 300
20%Economy
Topping floor for confectionery shop

FLOOR ENGINEERING CONSTRUCTION Topping floor for confectionery shop

Kaluga region, Maloyaroslavetsky district, Berezovka village
Characteristics and description
Company name
Private person
The purpose of the floor and the room itself
Topping floor for confectionery shop
Type of floor
topping floors
Thickness of the concrete layer
150 cm
Room area
540 sq. m.

Customer needs AND THE OPTIMAL ENGINEERING SOLUTION

factors taken into account when developing the floor design

WE HAVE CHOSEN THE OPTIMAL ENGINEERING SOLUTION

The building is some kind of old agricultural facility (most likely, either a storage facility or a primary processing workshop). The customer needed to align the base for the room with the equipment. He has a confectionery shop – the production of oriental sweets. And it was also necessary to make two ramps – a check-in and an exit. An important condition is that the customer wanted a technical solution that would require minimal costs to implement.


We proposed a concrete floor with a reinforcing top layer, reinforced with mesh on the ramps, and macrofibre in the room itself. This option suited the client, so they stopped at it.

The following aspects are important to the customer:

Terms of work
Number of days for all work: 20
Requirements for the quality of work
Floors must comply with SNiP 2.03. 13-88
Appearance of floors
Must look presentable
Durability
Service life of floors without repair (years): 5
Total cost
Budget within the framework of: 606 800 ₽
Topping floor for confectionery shop: The object before the start of work
The object before the start of work

Floor arrangement ACCORDING TO THE ENGINEERING SOLUTION FOR THE OBJECT: Private person

how we implemented this floor design

FEATURES OF THE WORKS

The only circumstance that made our work at least somewhat difficult was that from the back of the building, where the filling was carried out, it was necessary first of all to bring grout machines. To solve this situation, the customer had his own forklift truck. The driver very skillfully and smartly transported the equipment to the opposite entrance to the room. Otherwise, all the stages went like clockwork.

OUR RESULTS

In the course of our work, the customer himself managed to lay communications – pipes for wiring. He liked the result. We hope for further cooperation.

Stages of implementation engineering design of the floor

engineering design of the floor
1.jpg
Some of the materials were brought and unloaded
2.jpg
The filling material was brought and unloaded
3.jpg
Preparatory work
4.jpg
Preparing the reinforcement mesh on the ramp
5.jpg
A car with a highway has arrived
6.jpg
We are preparing a concrete mixture for pouring
7.jpg
The filling of the room has begun
8.jpg
Filling the ramp
9.jpg
The process of cutting shrinkage seams
10.jpg
Seams are cut

The result of floor engineeringDELIVERED ON TIME, STANDARD, TECHNOLOGICAL INDUSTRIAL FLOORS AT THE FACILITY Private person

SEE THE RESULT OF OUR WORK
result-somon-berezovka.jpg

READ REVIEWS OUR SATISFIED CUSTOMERS

Reviews that we managed to collect between production cycles at our facilities

ReviewsABOUT THE PROFTEHPOL PROJECT

We are well aware that reviews of companies can be very different. Working in the construction market for more than 15 years, we have faced various situations.

We have both satisfied customers and those who are not. But, there is one important thing: we always bring the cycles of our provision to the end. If a client has problems, then we do not leave him with them, but settle them to a full and final conclusion.

Working with us, you can be sure that we will make you an industrial floor that is exactly right for the task for which you needed it.

Thanks to a good knowledge of the technology of industrial floors, we have gathered a lot of practical experience in using floor structures in various difficult places. We solve non-trivial problems and often, when we take an order, 3-4 companies have already tried to take it before us, but refused due to the complexity of the object.

Our clients Which we are proud of

for which we have made good floors
Legal informationSociety Limited Liability "PROFTECHENGINEERING" Shareholdt International consumer society "GOLDEN AXIS"TIN 9709064635CHECKPOINT 770901001OGRN 1207700295406Legal address:109147, Moscow, B.Andronevskaya str., 23, building 1, floor 8, room 4, office of PROFTEHPOL company
POSTAL DETAILSActual address:109147, Moscow, B.Andronevskaya str., 23, building 1, floor 8, room 4, office of PROFTEHPOL companyPhone number for details:8 800 550 90 72E-mail:info@proftechpol.ru
Financial detailsCurrent account: 40702810870010234730MOSCOW BRANCH OF JSC CB "MODULBANK" MoscowBIC 044525092Correspondent account 30101810645250000092CEO of Nazyrov Anton