Our engineering in action
On the example of the floor arrangement for the largest transport and logistics center of Belarus "Prilesye"

INDUSTRIAL FLOOR AT THE METAL ROLLING WAREHOUSE IN PODOLSK

WE HAVE SAVED FOR THE CLIENT 129 600

FLOOR ENGINEERING CONSTRUCTION Topping floor for metal rolling warehouse in Podolsk

MO, Podolsk, Bolshoe Tolbino, Promyshlennaya str., building No. 7
Characteristics and description
Company name
JSC "Metallokomplekt-M"
The purpose of the floor and the room itself
Topping floor for metal rolling warehouse in Podolsk
Type of floor
topping floors
Thickness of the concrete layer
170 cm
Room area
104 m²

Customer needs AND THE OPTIMAL ENGINEERING SOLUTION

factors taken into account when developing the floor design

WE HAVE CHOSEN THE OPTIMAL ENGINEERING SOLUTION

Large metal products are produced in the customer's premises. We were required to fill the floor on a relatively small area of 104 m2. It was necessary to make this platform just for the final inspection of the finished product.

The customer asked to make a very smooth final coating, and one half had to be made simply concrete, and the other with topping. This wish was justified by the fact that the floor without topping is not rough. The client had previously had the experience of coating with a reinforcing top layer – it was quite slippery when people came in from the street in snow-wet shoes.

The following aspects are important to the customer:

Terms of work
Number of days for all work: 14
Requirements for the quality of work
Floors must comply with SNiP 2.03. 13-88
Appearance of floors
Must look presentable
Durability
Service life of floors without repair (years): 10
Total cost
Budget within the framework of: 648 200 ₽
Topping floor for metal rolling warehouse in Podolsk: The object before the start of work
The object before the start of work

Floor arrangement ACCORDING TO THE ENGINEERING SOLUTION FOR THE OBJECT: JSC "Metallokomplekt-M"

how we implemented this floor design

FEATURES OF THE WORKS

The floor had a crushed stone base. We had to put a formwork, and with a crushed stone base it is not so strong. Since we couldn't not make the formwork around the perimeter, we first chose one technical solution. During the implementation of this option, it became obvious that the frame was not particularly rigid. They figured it out in time and slightly changed their approach. As a result, the formwork turned out as it should.

OUR RESULTS

The client's company is a joint–stock company, their head office is located in Moscow, and he himself is located in the village of Bolshoe Tolbino. Usually in such cases, all the issues related to paperwork, payment, etc. take longer than usual. Even in the contract, these temporary nuances were taken into account. But after we delivered the fully finished coverage, they paid faster than expected. We can assume that this is a confirmation of high-quality work on our part.

Stages of implementation engineering design of the floor

engineering design of the floor
1.jpg
Materials have arrived at the facility
2.jpg
In agreement with the customer, the markup was made
3.jpg
The equipment arrived
4.jpg
Installation of formwork
5.jpg
Remaking the formwork fastening
6.jpg
The formwork is ready, the film is laid
7.jpg
The first mixer has arrived
8.jpg
Using a vibrating rack
9.jpg
The second mixer is at work
10.jpg
Completed the fill
11.jpg
Applying topping
12.jpg
Topping grout stage
13.jpg
They threw all the garbage into the container
14.jpg
They folded the formwork next to the stove
15.jpg
We apply varnish on half of the plate with topping
16.jpg
Finished plate from the topping side
17.jpg
The finished stove on the other side
18.jpg
Cutting of shrinkage seams
19.jpg
Measurement of the shrinkage seam
20.jpg
Sealing of shrinkage joints

The result of floor engineeringDELIVERED ON TIME, STANDARD, TECHNOLOGICAL INDUSTRIAL FLOORS AT THE FACILITY JSC "Metallokomplekt-M"

SEE THE RESULT OF OUR WORK
result-metallokomplekt-m.jpg

READ REVIEWS OUR SATISFIED CUSTOMERS

Reviews that we managed to collect between production cycles at our facilities

ReviewsABOUT THE PROFTEHPOL PROJECT

We are well aware that reviews of companies can be very different. Working in the construction market for more than 15 years, we have faced various situations.

We have both satisfied customers and those who are not. But, there is one important thing: we always bring the cycles of our provision to the end. If a client has problems, then we do not leave him with them, but settle them to a full and final conclusion.

Working with us, you can be sure that we will make you an industrial floor that is exactly right for the task for which you needed it.

Thanks to a good knowledge of the technology of industrial floors, we have gathered a lot of practical experience in using floor structures in various difficult places. We solve non-trivial problems and often, when we take an order, 3-4 companies have already tried to take it before us, but refused due to the complexity of the object.

Our clients Which we are proud of

for which we have made good floors
Legal informationSociety Limited Liability "PROFTECHENGINEERING" Shareholdt International consumer society "GOLDEN AXIS"TIN 9709064635CHECKPOINT 770901001OGRN 1207700295406Legal address:109147, Moscow, B.Andronevskaya str., 23, building 1, floor 8, room 4, office of PROFTEHPOL company
POSTAL DETAILSActual address:109147, Moscow, B.Andronevskaya str., 23, building 1, floor 8, room 4, office of PROFTEHPOL companyPhone number for details:8 800 550 90 72E-mail:info@proftechpol.ru
Financial detailsCurrent account: 40702810870010234730MOSCOW BRANCH OF JSC CB "MODULBANK" MoscowBIC 044525092Correspondent account 30101810645250000092CEO of Nazyrov Anton