Our engineering in action
On the example of the floor arrangement for the largest transport and logistics center of Belarus "Prilesye"

TOPPING FLOOR FOR AN OFFICE IN THE BUSINESS CENTER OF MOSCOW

WE HAVE SAVED FOR THE CLIENT 699 500

FLOOR ENGINEERING CONSTRUCTION Topping floor for office in Moscow on Semenovskaya lane

Moscow, Semenovsky lane, 15
Characteristics and description
Company name
LLC "K2"
The purpose of the floor and the room itself
Topping floor for office in Moscow on Semenovskaya lane
Type of floor
topping floors
Thickness of the concrete layer
140 cm
Room area
977.45 m²

Customer needs AND THE OPTIMAL ENGINEERING SOLUTION

factors taken into account when developing the floor design

WE HAVE SELECTED THE OPTIMAL ENGINEERING SOLUTION

The year before last, this customer – the general contracting organization – already ordered from us the execution of the floor in the same building on the tenth floor. This time we were asked for a floor arrangement in a room of about the same area and about the same type, but already on the 9th floor. It was necessary to arrange a concrete floor with two types of topping – gray and black.

The following aspects are important to the customer:

Terms of work
Number of days for all work: 18
Requirements for the quality of work
Floors must comply with SNiP 2.03. 13-88
Appearance of floors
Must look presentable
Durability
Service life of floors without repair (years): 10
Total cost
Budget within the framework of: 3 497 500 ₽
Topping floor for office in Moscow on Semenovskaya lane: The object before the start of work
The object before the start of work

Floor arrangement ACCORDING TO THE ENGINEERING SOLUTION FOR THE OBJECT: LLC "K2"

how we implemented this floor design

FEATURES OF THE WORKS

Over the past year, work at this facility has proved to be the most difficult.

First, the delivery of topping. Previously, we ordered Sica topping for work on the 10th floor. At the same time, due to the situation in the country, this supplier did not have the topping we needed. I had to look for other options. As a result, they found it – from the company Monopol.

The foreman of the brigade assigned to this facility urgently had to leave for family reasons. The customer refused our offer to postpone the start of work for one day. We found other workers. There were a lot of wires and sockets all over the area of the room. These workers, seeing all the complexity, immediately ran away. As a result, the initial team started the work.

Since the room is located on the 9th floor, the delivery of equipment and materials there was planned via an elevator. In fact, it turned out not to be so – a lot of things did not fit in the elevator. Therefore, the grid was lifted manually by a ladder; a crane was ordered to move the equipment, which led to additional costs.

OUR RESULTS

We have performed the work at the highest possible level of quality. The customer informed that in the same building there is another room on the ground floor where a new floor is required. And in general, this general contractor has and plans many facilities. Therefore, we expect that we will cooperate more than once.

Stages of implementation engineering design of the floor

engineering design of the floor
1.jpg
Two layers of film were laid on the first fill
2.jpg
We started gluing the tape
3.jpg
Raised the equipment
4.jpg
We finish knitting the mesh for the first filling
5.jpg
The mixer has arrived
6.jpg
The track was assembled, the pipes were pumped
7.jpg
First fill
8.jpg
Seams were cut on the first square, cleaning was done
9.jpg
Glue the tape on the second fill
10.jpg
The net is laid and tied; the chairs are laid
11.jpg
The pump has arrived
12.jpg
Place of flushing of trays and pump
13.jpg
We accept concrete
14.jpg
Grout stage
15.jpg
A third of the site is patched up
16.jpg
Cleaning
17.jpg
The warm contour on the floor has been restored
18.jpg
Sawing shrinkage seams

The result of floor engineeringDELIVERED ON TIME, STANDARD, TECHNOLOGICAL INDUSTRIAL FLOORS AT THE FACILITY LLC "K2"

SEE THE RESULT OF OUR WORK
result-object-2.jpg

READ REVIEWS OUR SATISFIED CUSTOMERS

Reviews that we managed to collect between production cycles at our facilities

ReviewsABOUT THE PROFTEHPOL PROJECT

We are well aware that reviews of companies can be very different. Working in the construction market for more than 15 years, we have faced various situations.

We have both satisfied customers and those who are not. But, there is one important thing: we always bring the cycles of our provision to the end. If a client has problems, then we do not leave him with them, but settle them to a full and final conclusion.

Working with us, you can be sure that we will make you an industrial floor that is exactly right for the task for which you needed it.

Thanks to a good knowledge of the technology of industrial floors, we have gathered a lot of practical experience in using floor structures in various difficult places. We solve non-trivial problems and often, when we take an order, 3-4 companies have already tried to take it before us, but refused due to the complexity of the object.

Our clients Which we are proud of

for which we have made good floors
Legal informationSociety Limited Liability "PROFTECHENGINEERING" Shareholdt International consumer society "GOLDEN AXIS"TIN 9709064635CHECKPOINT 770901001OGRN 1207700295406Legal address:109147, Moscow, B.Andronevskaya str., 23, building 1, floor 8, room 4, office of PROFTEHPOL company
POSTAL DETAILSActual address:109147, Moscow, B.Andronevskaya str., 23, building 1, floor 8, room 4, office of PROFTEHPOL companyPhone number for details:8 800 550 90 72E-mail:info@proftechpol.ru
Financial detailsCurrent account: 40702810870010234730MOSCOW BRANCH OF JSC CB "MODULBANK" MoscowBIC 044525092Correspondent account 30101810645250000092CEO of Nazyrov Anton