Our engineering in action
On the example of the floor arrangement for the largest transport and logistics center of Belarus "Prilesye"

TOPPING FLOOR FOR A PRODUCTION FACILITY NEAR VNUKOVO

WE HAVE SAVED FOR THE CLIENT 318 300
20%Economy
Topping floor for production facility near Vnukovo

FLOOR ENGINEERING CONSTRUCTION Topping floor for production facility near Vnukovo

Moscow, Vnukovo settlement, Zavodskoe shosse, 19c49
Characteristics and description
Company name
NPO INAKON LLC
The purpose of the floor and the room itself
Topping floor for production facility near Vnukovo
Type of floor
topping floors
Thickness of the concrete layer
13 cm
Room area
347.2 m²

Customer needs AND THE OPTIMAL ENGINEERING SOLUTION

factors taken into account when developing the floor design

WE HAVE SELECTED THE OPTIMAL ENGINEERING SOLUTION

After the first acquaintance with the client and his object, the idea arose to make a concrete floor with combined reinforcement – over the entire area with plastic fiber and in several sections with a reinforcement frame in one layer.

However, further technical examination showed that the existing concrete base could not be called load-bearing due to its small thickness and other factors. As a result, the technical solution was aimed at creating a reliable load–bearing floor and sounded like this - a topping floor with an average thickness of 130 mm reinforced with steel fiber.

Terms of work
Number of days for all work: 5
Requirements for the quality of work
Floors must comply with SNiP 2.03. 13-88
Appearance of floors
Must look presentable
Durability
Service life of floors without repair (years): 10
Total cost
Budget within the framework of: 1 591 700 ₽
Topping floor for production facility near Vnukovo: The object before the start of work
The object before the start of work

Floor arrangement ACCORDING TO THE ENGINEERING SOLUTION FOR THE OBJECT: NPO INAKON LLC

how we implemented this floor design

FEATURES OF THE WORK

Due to the changed technical solution, the fittings brought to the facility had to be taken to the warehouse. It's still there, but fortunately, some of it has already been used elsewhere recently.

This production facility is located very close to Vnukovo airport and therefore is a closed facility. To get to the facility, workers and machines were coordinated and issued passes.

OUR RESULTS

As a result of all the work, the client received a modern concrete floor with a durable coating in his production, which, with proper care, will last for decades.

Stages of implementation engineering design of the floor

engineering design of the floor
1.jpg
Sand ramming
2.jpg
Preparation
3.jpg
Fill
4.jpg
Grout
5.jpg
After grouting, a membrane forming agent has been applied
6.jpg
Cutting seams
7.jpg
The seams have been cut
8.jpg
Sealing of seams has been performed

The result of floor engineeringDELIVERED ON TIME, STANDARD, TECHNOLOGICAL INDUSTRIAL FLOORS AT THE FACILITY NPO INAKON LLC

SEE THE RESULT OF OUR WORK
result-inakon-vnukovo.jpg

READ REVIEWS OUR SATISFIED CUSTOMERS

Reviews that we managed to collect between production cycles at our facilities

ReviewsABOUT THE PROFTEHPOL PROJECT

We are well aware that reviews of companies can be very different. Working in the construction market for more than 15 years, we have faced various situations.

We have both satisfied customers and those who are not. But, there is one important thing: we always bring the cycles of our provision to the end. If a client has problems, then we do not leave him with them, but settle them to a full and final conclusion.

Working with us, you can be sure that we will make you an industrial floor that is exactly right for the task for which you needed it.

Thanks to a good knowledge of the technology of industrial floors, we have gathered a lot of practical experience in using floor structures in various difficult places. We solve non-trivial problems and often, when we take an order, 3-4 companies have already tried to take it before us, but refused due to the complexity of the object.

Our clients Which we are proud of

for which we have made good floors
Legal informationSociety Limited Liability "PROFTECHENGINEERING" Shareholdt International consumer society "GOLDEN AXIS"TIN 9709064635CHECKPOINT 770901001OGRN 1207700295406Legal address:109147, Moscow, B.Andronevskaya str., 23, building 1, floor 8, room 4, office of PROFTEHPOL company
POSTAL DETAILSActual address:109147, Moscow, B.Andronevskaya str., 23, building 1, floor 8, room 4, office of PROFTEHPOL companyPhone number for details:8 800 550 90 72E-mail:info@proftechpol.ru
Financial detailsCurrent account: 40702810870010234730MOSCOW BRANCH OF JSC CB "MODULBANK" MoscowBIC 044525092Correspondent account 30101810645250000092CEO of Nazyrov Anton