Floor arrangement ACCORDING TO THE ENGINEERING SOLUTION FOR THE OBJECT: SNITCH LLC
how we implemented this floor design
FEATURES OF THE WORK
After signing the contract, the premise was not immediately ready for transfer to us. Our foreman went to the facility and supervised the process, showing what needed to be removed, what needed to be swept, what needed to be foamed, etc. The customer's workers promptly followed all instructions, and we delivered and placed materials in parallel.
The walls and columns were painted white to protect them from contamination with a film.
The room was located on the second floor, so a boom concrete pump was used for pouring.
OUR RESULTS
Since the deadlines were tight, we did all the work faster than usual. As a result, we made it on time and completed the work by cutting seams before the January holidays. Yes, there is still sealing the seams, but this will be completed in a separate step in a few weeks.