Our engineering in action
On the example of the floor arrangement for the largest transport and logistics center of Belarus "Prilesye"

TOPPING FLOOR FOR THE WORKSHOP IN APRELEVKA

WE HAVE SAVED FOR THE CLIENT 520 300

FLOOR ENGINEERING CONSTRUCTION Topping floor for the shop in Aprelevka

MO, Aprelevka, Parkovaya str., 1
Characteristics and description
Company name
Ivotsteklo LLC
The purpose of the floor and the room itself
Topping floor for the shop in Aprelevka
Type of floor
topping floors
Thickness of the concrete layer
13 cm
Room area
902 m²

Customer needs AND THE OPTIMAL ENGINEERING SOLUTION

factors taken into account when developing the floor design

WE HAVE SELECTED THE OPTIMAL ENGINEERING SOLUTION

The customer rented out his workshop for some time, and the foundation at the time of contacting us was no longer smooth, with destruction. The client planned to use the room for his tasks after the work. It was necessary to perform routine floor repairs.

The technical solution was chosen as standard – a topping floor with an average thickness of 130 mm, reinforced with plastic macrofibre over the entire area and in some places additionally reinforced with a mesh with a diameter of 5 mm.

Terms of work
Number of days for all work: 5
Requirements for the quality of work
Floors must comply with SNiP 2.03. 13-88
Appearance of floors
Must look presentable
Durability
Service life of floors without repair (years): 10
Total cost
Budget within the framework of: 2 601 700 ₽
Topping floor for the shop in Aprelevka: The object before the start of work
The object before the start of work

Floor arrangement ACCORDING TO THE ENGINEERING SOLUTION FOR THE OBJECT: Ivotsteklo LLC

how we implemented this floor design

FEATURES OF THE WORK

There was a sharp drop in the thickness of the concrete layer in the trenches, so they were additionally reinforced with mesh in order to prevent cracks.

Even at the stage of forming the estimate, we determined that we would pour directly from the mixer with self-watering. But before starting work on the installation of a concrete floor, the client laid electrical cables at the facility. In order not to damage them, the rental of a concrete pump was agreed with the customer.

The facility had a 1.5 meter deep pit. The customer thought to fill it with concrete, but this option would be too costly and generally suboptimal. We solved the situation like this: we asked the customer to fill it with sand, tamp it down and leave a small pit with a depth of 150 mm on top.

OUR RESULTS

As a result of all the production stages, a durable and beautiful industrial floor appeared in the workshop, designed for long-term operation without loss of production characteristics.

Stages of implementation engineering design of the floor

engineering design of the floor
1.jpg
Completed the preparatory work
2.jpg
Filling of fiber into concrete
3.jpg
Filling
4.jpg
Finished grout
5.jpg
Applied the varnish
6.jpg
Sealed seams

The result of floor engineeringDELIVERED ON TIME, STANDARD, TECHNOLOGICAL INDUSTRIAL FLOORS AT THE FACILITY Ivotsteklo LLC

SEE THE RESULT OF OUR WORK
result-ivotsteklo-aprelevka.jpg

READ REVIEWS OUR SATISFIED CUSTOMERS

Reviews that we managed to collect between production cycles at our facilities

ReviewsABOUT THE PROFTEHPOL PROJECT

We are well aware that reviews of companies can be very different. Working in the construction market for more than 15 years, we have faced various situations.

We have both satisfied customers and those who are not. But, there is one important thing: we always bring the cycles of our provision to the end. If a client has problems, then we do not leave him with them, but settle them to a full and final conclusion.

Working with us, you can be sure that we will make you an industrial floor that is exactly right for the task for which you needed it.

Thanks to a good knowledge of the technology of industrial floors, we have gathered a lot of practical experience in using floor structures in various difficult places. We solve non-trivial problems and often, when we take an order, 3-4 companies have already tried to take it before us, but refused due to the complexity of the object.

Our clients Which we are proud of

for which we have made good floors
Legal informationSociety Limited Liability "PROFTECHENGINEERING" Shareholdt International consumer society "GOLDEN AXIS"TIN 9709064635CHECKPOINT 770901001OGRN 1207700295406Legal address:109147, Moscow, B.Andronevskaya str., 23, building 1, floor 8, room 4, office of PROFTEHPOL company
POSTAL DETAILSActual address:109147, Moscow, B.Andronevskaya str., 23, building 1, floor 8, room 4, office of PROFTEHPOL companyPhone number for details:8 800 550 90 72E-mail:info@proftechpol.ru
Financial detailsCurrent account: 40702810870010234730MOSCOW BRANCH OF JSC CB "MODULBANK" MoscowBIC 044525092Correspondent account 30101810645250000092CEO of Nazyrov Anton