Our engineering in action
On the example of the floor arrangement for the largest transport and logistics center of Belarus "Prilesye"

INDUSTRIAL FLOOR FOR THE WORKSHOP IN THE RAZVILKA VILLAGE

WE HAVE SAVED FOR THE CLIENT 162 000
20%Economy
Topping floor for the workshop in the Razvilka

FLOOR ENGINEERING CONSTRUCTION Topping floor for the workshop in the Razvilka

Moscow region, Leninsky G.O., p. Razvilka, Projected avenue No. 5537, vl. 4, p. 17
Characteristics and description
Company name
JSC "Moscow Gas Processing Plant"
The purpose of the floor and the room itself
Topping floor for the workshop in the Razvilka
Type of floor
topping floors
Thickness of the concrete layer
120 cm
Room area
340 sq. m.

Customer needs AND THE OPTIMAL ENGINEERING SOLUTION

factors taken into account when developing the floor design

FOUND OUT THE NEEDS OF THE CLIENT

The task for this object sounded like this: it is necessary to update the floor in one of the production premises; for this, a new concrete floor reinforced with welded mesh with a reinforced top layer – topping is required on top of the old concrete base; the floor must be made into the horizon; it must withstand cargo loads.

The following aspects are important to the customer:

Terms of work
Number of days for all work: 30
Requirements for the quality of work
Floors must comply with SNiP 2.03. 13-88
Appearance of floors
Must look presentable
Durability
Service life of floors without repair (years): 20
Total cost
Budget within the framework of: 810 000 ₽
Topping floor for the workshop in the Razvilka: The object before the start of work
The object before the start of work

Floor arrangement ACCORDING TO THE ENGINEERING SOLUTION FOR THE OBJECT: JSC "Moscow Gas Processing Plant"

how we implemented this floor design

DIFFICULTIES DURING WORK

Already during the installation of the floor, some points emerged that entailed additional work not provided for in the plan. Also, after the dismantling was completed, there was a moment of coordination with the customer of the increased supply of concrete to the facility.

OUR RESULTS

The resulting floor was liked by the customer, all stages were completed within the agreed time frame. We worked in the village of Razvilka for the first time and thereby opened an account for our ready-made objects in this locality.

Stages of implementation engineering design of the floor

engineering design of the floor
1.jpg
We deliver the equipment
2.jpg
We deliver the equipment
3.jpg
The floor is ready to fill
4.jpg
The first mixer got up for unloading
5.jpg
The second mixer is in place
6.jpg
We accept a concrete mixture
7.jpg
We accept a concrete mixture
8.jpg
Leveling the concrete
9.jpg
We seal the concrete layer
10.jpg
Completed the grout stage
11.jpg
There is a cutting of shrinkage seams
12.jpg
Cut the seams

The result of floor engineeringDELIVERED ON TIME, STANDARD, TECHNOLOGICAL INDUSTRIAL FLOORS AT THE FACILITY JSC "Moscow Gas Processing Plant"

SEE THE RESULT OF OUR WORK
result-mpgz.jpg

READ REVIEWS OUR SATISFIED CUSTOMERS

Reviews that we managed to collect between production cycles at our facilities

ReviewsABOUT THE PROFTEHPOL PROJECT

We are well aware that reviews of companies can be very different. Working in the construction market for more than 15 years, we have faced various situations.

We have both satisfied customers and those who are not. But, there is one important thing: we always bring the cycles of our provision to the end. If a client has problems, then we do not leave him with them, but settle them to a full and final conclusion.

Working with us, you can be sure that we will make you an industrial floor that is exactly right for the task for which you needed it.

Thanks to a good knowledge of the technology of industrial floors, we have gathered a lot of practical experience in using floor structures in various difficult places. We solve non-trivial problems and often, when we take an order, 3-4 companies have already tried to take it before us, but refused due to the complexity of the object.

Our clients Which we are proud of

for which we have made good floors
Legal informationSociety Limited Liability "PROFTECHENGINEERING" Shareholdt International consumer society "GOLDEN AXIS"TIN 9709064635CHECKPOINT 770901001OGRN 1207700295406Legal address:109147, Moscow, B.Andronevskaya str., 23, building 1, floor 8, room 4, office of PROFTEHPOL company
POSTAL DETAILSActual address:109147, Moscow, B.Andronevskaya str., 23, building 1, floor 8, room 4, office of PROFTEHPOL companyPhone number for details:8 800 550 90 72E-mail:info@proftechpol.ru
Financial detailsCurrent account: 40702810870010234730MOSCOW BRANCH OF JSC CB "MODULBANK" MoscowBIC 044525092Correspondent account 30101810645250000092CEO of Nazyrov Anton