TOPPING FLOOR IN A WAREHOUSE IN THE NIZHEGORODSKY DISTRICT OF MOSCOW

WE HAVE SAVED FOR THE CLIENT 462 900
20%Economy
Topping floor in a warehouse in the Nizhegorodsky district of Moscow

FLOOR ENGINEERING CONSTRUCTION Topping floor in a warehouse in the Nizhegorodsky district of Moscow

17A Frezer Highway, Building 2, Moscow
Characteristics and description
Company name
LLC Trading and Manufacturing Company NVN
The purpose of the floor and the room itself
Topping floor in a warehouse in the Nizhegorodsky district of Moscow
Type of floor
topping floors
Thickness of the concrete layer
13 cm
Room area
627.7 m²

Customer needs AND THE OPTIMAL ENGINEERING SOLUTION

factors taken into account when developing the floor design

WE HAVE SELECTED THE OPTIMAL ENGINEERING SOLUTION

A client who had us do a floor in a warehouse in 2023 came back to us for work on another room at the same address. Our standard phone interview and site visit provided the design department with all the information they needed.

A technical solution was developed: a 13 cm thick topping floor reinforced with plastic fiber and additionally reinforced with a 10 mm diameter frame in several places.

The scope of work also included the construction of two ramps with the preliminary demolition of the corresponding sections.

Terms of work
Number of days for all work: 30
Requirements for the quality of work
Floors must comply with SNiP 2.03. 13-88
Appearance of floors
Must look presentable
Durability
Service life of floors without repair (years): 10
Total cost
Budget within the framework of: 2 314 300 ₽
Topping floor in a warehouse in the Nizhegorodsky district of Moscow: The object before the start of work
The object before the start of work

Floor arrangement ACCORDING TO THE ENGINEERING SOLUTION FOR THE OBJECT: LLC Trading and Manufacturing Company NVN

how we implemented this floor design

FEATURES OF WORKS

There were several tenants in the building, so we only worked on our client's property.

The customer dug a trench on their own. We additionally reinforced the area above it with a frame of reinforcing bars.

It was hot, +27 degrees Celsius. The concrete hardened very quickly, so we had to work fast.

We didn't accept one of the concrete mixers that arrived, and we turned it back because the mixture was already thick.

OUR RESULTS

The work on this project was not easy, but thanks to our clear actions based on our standard technology and the customer's support at all stages, we achieved success.

Stages of implementation engineering design of the floor

engineering design of the floor
1.jpg
Received delivery from Petrovich
2.jpg
The corners for the ramp are ready
3.jpg
Installation of an isolation joint around a column
4.jpg
Assembling the concrete pump line
5.jpg
Mixer has arrived
6.jpg
Pouring has started
7.jpg
Concrete compaction with a vibrating screed
8.jpg
Pouring has been completed
9.jpg
Surface treatment with a grinding machine
10.jpg
Troweling in progress
11.jpg
Moisture-retaining impregnation applied
12.jpg
Floor levelness check
13.jpg
Marking of shrink joints
14.jpg
Cutting of joints in progress
15.jpg
Checking joint depth
16.jpg
Cut shrink joints

The result of floor engineeringDELIVERED ON TIME, STANDARD, TECHNOLOGICAL INDUSTRIAL FLOORS AT THE FACILITY LLC Trading and Manufacturing Company NVN

SEE THE RESULT OF OUR WORK
result-tpk-nvn-frezer-2025.jpg

READ REVIEWS OUR SATISFIED CUSTOMERS

Reviews that we managed to collect between production cycles at our facilities

ReviewsABOUT THE PROFTEHPOL PROJECT

We are well aware that reviews of companies can be very different. Working in the construction market for more than 15 years, we have faced various situations.

We have both satisfied customers and those who are not. But, there is one important thing: we always bring the cycles of our provision to the end. If a client has problems, then we do not leave him with them, but settle them to a full and final conclusion.

Working with us, you can be sure that we will make you an industrial floor that is exactly right for the task for which you needed it.

Thanks to a good knowledge of the technology of industrial floors, we have gathered a lot of practical experience in using floor structures in various difficult places. We solve non-trivial problems and often, when we take an order, 3-4 companies have already tried to take it before us, but refused due to the complexity of the object.

Our clients Which we are proud of

for which we have made good floors
Legal informationSociety Limited Liability "PROFTECHENGINEERING" Shareholdt International consumer society "GOLDEN AXIS"TIN 9709064635CHECKPOINT 770901001OGRN 1207700295406Legal address:109147, Moscow, B.Andronevskaya str., 23, building 1, floor 8, room 4, office of PROFTEHPOL company
POSTAL DETAILSActual address:109147, Moscow, B.Andronevskaya str., 23, building 1, floor 8, room 4, office of PROFTEHPOL companyPhone number for details:8 800 550 90 72E-mail:info@proftechpol.ru
Financial detailsCurrent account: 40702810870010234730MOSCOW BRANCH OF JSC CB "MODULBANK" MoscowBIC 044525092Correspondent account 30101810645250000092CEO of Nazyrov Anton