Floor arrangement ACCORDING TO THE ENGINEERING SOLUTION FOR THE OBJECT: АО «6-й таксомоторный парк»
how we implemented this floor design
FEATURES OF THE WORK
We have divided the first stage, the dismantling work, into two parts. First, the main part with an area of about 600 m2, and then the remaining plot. To dismantle the main area, we used a remote-controlled robot, but also worked manually.
We had to try with the arrangement of the trays – they were of different lengths, widths and depths. It was also not easy with sand traps, since the original products were small. We dug two large pits, filled the foundations for the concrete containers brought by the customer, connected them to the trays and thus obtained a suitable design.
Due to the large number of trays, the floor design assumed the presence of slopes from different sides. To do this, the sandy base was prepared immediately at an angle, and then guides were installed.
OUR RESULTS
The car wash now boasts a modern, durable concrete floor that meets all production requirements, as well as a modern functional system of trays and sand traps.