Floor arrangement ACCORDING TO THE ENGINEERING SOLUTION FOR THE OBJECT: Association of real estate owners "MY HOUSE"
how we implemented this floor design
FEATURES OF THE WORK
At first, it was assumed that it would be necessary to pull a concrete pump track of 150 linear meters, which did not look like an effective solution in any way. As a result, in coordination with the customer's representatives, they found a way out – they ran the route through the landing and thereby halved the length.
In addition to the main square, there were also several sections, to which the highway was separately completed.
The work was planned to be done in one pour, but an accident happened – the mixer ran over the concrete pump and broke an important detail, which made further concrete supply impossible. I had to perform the remaining section in another stage.
OUR RESULTS
Thanks to the comprehensive assistance of the customer throughout all stages of the work, they were able to be completed as quickly and efficiently as possible. The underground parking of the residential building has now been provided with a modern and durable floor for years.