Floor arrangement ACCORDING TO THE ENGINEERING SOLUTION FOR THE OBJECT: Dmitrov Foundry and Mechanical Plant LLC
how we implemented this floor design
FEATURES OF THE WORK
Initially, before signing the contract, we calculated the exact amount of concrete needed to make a flat floor over the entire area. However, right before pouring, the client informed that it was necessary to raise the floor level so that it coincided with the level of the cold shop outside. We quickly recalculated the volume of concrete and fiber and signed an additional agreement.
On the day the facility was prepared for pouring, additional work was performed to reduce the consumption of concrete – in several places, crushed stone was first filled in, compacted, tamped, and corners were placed in different places.
Even before our arrival, the client himself painted the columns a bright orange color. To protect the surfaces from contamination, workers wrapped the walls and columns with film.
OUR RESULTS
The client received excellent concrete floors with topping for three rooms of his plant, taking into account all available loads and production features. In the future, he plans to work on the floors and other areas. We look forward to continuing our cooperation as soon as possible.