Floor arrangement ACCORDING TO THE ENGINEERING SOLUTION FOR THE OBJECT: Individual entrepreneur
how we implemented this floor design
FEATURES OF THE WORK
At first, the customer thought that the ramp device would not be included in the work package. But before starting work, he still decided differently, so they issued an additional agreement. By the way, the reinforcement on the ramp was made combined – a reinforcement frame in one layer plus plastic fiber.
There was no place to clean the mixers after unloading the concrete in the area nearby the facility. To solve this issue, we have included in the estimate in advance the amount for collecting wooden boxes.
On the day of cutting the seams, the filling result was checked by the customer. He did not like the uneven edge of the ramp, and there were also comments about the broken topping in some places near the tray. On the same day, all the shortcomings were eliminated.
They planned to come and do the sealing of the seams after the deadline set by the norms, but the client refused it – he said that they would do it on their own.
OUR RESULTS
Actions speak better than any words about the results. After the final acceptance of all the works from his company, our foreman was presented with a bouquet of his own production as a sign of gratitude.