WE HAVE SELECTED THE OPTIMAL ENGINEERING SOLUTION
A prefabricated warehouse was being built in the city of Vidnoye, Moscow region, and at the same time, work on the floor was urgently needed. Initially, the client stated that the expected loads would be up to 7 tons per 1 m2, and we prepared a design calculation for these figures.
But then we made calculations based on the data provided by the customer, and it turned out that not 7 tons, but 5 tons per 1 m2. The client, having studied our calculations, agreed. As a result, the design was chosen as follows: a concrete floor with an average thickness of 150 mm, reinforced with steel fiber.