Floor arrangement ACCORDING TO THE ENGINEERING SOLUTION FOR THE OBJECT: REAL CONTINENT M LLC
how we implemented this floor design
FEATURES OF THE WORK
We proposed to the client and agreed with him on the installation of 3 permanent formworks – 2 transverse lines and 1 longitudinal line, which ultimately divided the entire area into 6 separate sections.
The facility was being built quickly, the customer was in a hurry – his company urgently needed to move from the rented warehouse. Several types of work were carried out simultaneously – the building was still being raised, and at the far end we were already carrying out the first fills. At the same time, another contractor was preparing the sand base in the following areas.
Even before signing the contract, we announced that we would complete all the main work in 6 pours and 12 days. And that's what happened.
An agreement was reached with the concrete plant to use better materials for the preparation of the mixture than usual in the area: cleaner crushed stone, good coarse-grained sand and cement without additives. Yes, it turned out to be a little more expensive, but it had a positive effect on the quality.
OUR RESULTS
We provided the client with the floor that he wanted – smooth and strong. It was also extremely important to complete the work as quickly as possible – and we successfully coped with this.